Standard version 5.0 April 2024

Section 0.1 Bibliography

Standards

Number and date Title
BS 4449:2005+A3:2016 Steel for the reinforcement of concrete – weldable reinforcing steel – bar, coil and decoiled product – specification
BS 4482:2005 Steel wire for the reinforcement of concrete products – Specification (AMD 17104)
BS 4483:2025 Steel fabric for the reinforcement of concrete – specification
BS 4486:1980 Specification for hot rolled and hot rolled and processed high tensile alloy steel bars for the prestressing of concrete.
BS 5606:2022 Accuracy and tolerance in design and construction. Guide
BS 5655-6:2011 Lifts and service lifts – Code of practice for the selection, installation and location of new lifts
BS 5896: 2012 High tensile steel wire and strand for the prestressing of concrete
BS 5975-1:2024 Temporary works. Management procedures for the control of temporary works – code of practice
BS 5975-2:2024 Temporary works. Falsework: Design and implementation – code of practice
BS 6744:2023 Stainless steel bars – Reinforcement of concrete – Requirements and test methods
BS 7542:1992 Method of test for curing compounds for concrete
BS 7973-1:2001 Spacers and chairs for steel reinforcement and their specification. Product performance requirements
BS 7973-2:2001 Spacers and chairs for steel reinforcement and their specification. Fixing and application of spacers and chairs and tying of reinforcement
BS 8102: 2022 Protection of below ground structures against water ingress — Code of practice
BS 8204-1:2003+A1:2009 Screeds, bases and in-situ floorings – Concrete bases and cementitious levelling screeds to receive floorings. Code of practice
BS 8204-2:2003+A2:2011 Screeds, bases and in situ floorings – Concrete wearing surfaces. Code of practice
BS 8204-3:2004+A2:2011 Screeds, bases and in situ floorings – Polymer modified cementitious levelling screeds and wearing screeds. Code of practice
BS 8204-4:2004+A1:2011 Screeds, bases and in situ floorings – Cementitious terrazzo wearing surfaces. Code of practice
BS 8204-5:2004+A1:2011 Screeds, bases and in situ floorings – Mastic asphalt underlays and wearing surfaces. Code of practice
BS 8204-6:2008(+A1:2010) Screeds, bases and in-situ floorings – Synthetic resin floorings. Code of practice
BS 8500-1:2023 Concrete – complementary British Standard to BS EN 206. Method of specifying and guidance for the specifier
BS 8500-2:2023 Concrete – complementary British Standard to BS EN 206. Specification for constituent materials and concrete
BS 8548:2017 Guidance for arc welding of reinforcing steel
BS 8597:2015 Steels for the reinforcement of concrete – reinforcement couplers – requirements and test methods
BS 8666: 2020 Scheduling, dimensioning, cutting and bending of steel reinforcement for concrete — Specification
BS 8902: 2009 Responsible sourcing sector certification schemes for construction products – Specification.
BS 99001: 2022 Quality management systems – Specification for the application of BS EN ISO 9001:2015 in the built environment sector (Incorporating Corrigendum No. 1)
BS EN 197-1:2011 Cement – Composition, specifications and conformity criteria for common cements
BS EN 197-5:2021 Cement. Portland-composite cement CEM II/C-M and Composite cement CEM VI
BS EN 206: 2013+A2:2021 Concrete – specification, performance, production and conformity
BS EN 445:2007 Grout for prestressing tendons – Test methods
BS EN 446:2007 Grout for prestressing tendons. Grouting procedures
BS EN 447:2007 Grout for prestressing tendons. Basic requirements
BS EN 934-1:2008 Admixtures for concrete, mortar and grout – Common requirements
BS EN 934-2:2009+A1:2012 Admixtures for concrete, mortar and grout – Concrete admixtures. Definitions, requirements, conformity, marking and labelling
BS EN 1090 Execution of steel structures and aluminium structures
BS EN 1090-2:2018+A1:2024 Execution of steel structures and aluminium structures – Technical requirements for steel structures
BS EN 1168:2005 Hollow core slabs
BS EN 1520:2011 Prefabricated reinforced components of lightweight aggregate concrete with open structure with structural or non-structural reinforcement
BS EN 1990:2002+A1:2005 Eurocode, Basis of structural design (incorporating corrigendum December 2008 and April 2010)
BS EN 1991 Eurocode 1, Actions on structures published in 10 parts
BS EN 1992-1-1: 2004 (+A1:2014) Eurocode 2, Design of concrete structures. General rules and rules for buildings (incorporating corrigenda January 2008, November 2010 and January 2014)
BS EN 1992-1-2: 2004 (+A1:2019) Eurocode 2, Design of concrete structures. General rules. Structural fire design (Incorporating corrigendum July 2008)
BS EN 1992-2: 2005 Eurocode 2, Design of concrete structures. Concrete bridges. Design and detailing rules (incorporating corrigendum July 2008)
BS EN 1992-3: 2006 Eurocode 2, Design of concrete structures. Liquid retaining and containing structures
BS EN 12350 Testing fresh concrete -published in 12 parts
BS EN 12620:2013 Aggregates for concrete
BS EN 12794:2005 Foundation piles
BS EN 12812:2008 Falsework – Performance requirements and general design
BS EN 12839:2012 Elements for fences
BS EN 12843:2004 Masts and poles
BS EN 13139:2002 Aggregates for mortar
BS EN 13224:2011 Ribbed floor elements
BS EN 13225:2013 Linear structural elements
BS EN 13369:2023 Common rules for precast concrete products
BS EN 13391:2004 Mechanical tests for post-tensioning systems
BS EN 13670: 2009 Execution of concrete structures (incorporating corrigenda October 2015 and November 2015)
BS EN 13693:2004+A1:2009 Special roof elements
BS EN 13747:2005+A2:2010 Floor plates for floor systems
BS EN 13978-1:2005 Precast concrete garages
BS EN 14487-2: 2006 Sprayed concrete. Execution
BS EN 14650:2005 Precast concrete products. General rules for factory production control of metallic fibered concrete
BS EN 14843:2007 Stairs
BS EN 14844:2006 Box culverts
BS EN 14991:2007 Foundation elements
BS EN 14992:2007+A1:2012 Wall elements
BS EN 15037 Precast concrete products. Beam and block floor systems published in 5 parts
BS EN 15050:2007 +A1:2012 Bridge elements
BS EN 15258:2008 Retaining wall elements
BS EN 15804:2012+A2:2019 Sustainability of construction works. Environmental product declarations. Core rules for the product category of construction products (Incorporating corrigenda February 2014, July 2020 and August 2021)
BS EN 16757:2022 Sustainability of construction works. Environmental product declarations. Product Category Rules for concrete and concrete elements
BS EN ISO 4157-1:1999 Construction drawings – designation systems. Buildings and parts of buildings
BS EN ISO 9001:2015+A1:2024 Quality management systems. Requirements
BS EN ISO 14001:2015+A1:2024 Environmental management systems – Requirements with guidance for use
BS EN ISO 14021:2016+A1:2021 Environmental labels and declarations – Self-declared environmental claims (Type II environmental labelling)
BS EN ISO 17660-1:2006 Welding – Welding of reinforcing steel. Load-bearing welded joints (incorporating corrigendum December 2008)
BS EN ISO 17660-2:2006 Welding – Welding of reinforcing steel. Non load-bearing welded joints (incorporating corrigendum December 2008)
BS EN ISO/IEC 17021-1:2015 Conformity assessment. Requirements for bodies providing audit and certification of management systems. Requirements
BS EN ISO/IEC 17025:2017 Competence of laboratories
BS EN ISO/IEC 17065:2012 Requirements for Certification Bodies
ISO 14484:2020 Performance guidelines for design of concrete structures using fibre-reinforced polymer (FRP) materials
ISO 22873:2021 Quality control for batching and mixing steel fibre-reinforced concretes
BSI Flex 350:2024 Alternative binder systems for lower carbon concrete – Code of practice
PAS 2080:2023 Carbon management in buildings and infrastructure
EAD 050019-00-0301:2019 Dowels for structural joints under static and quasi-static loading
EAD 160003-00-0301:2018 Double headed studs for the increase of punching shear resistance of flat slabs or footings and ground slabs
EAD 160004-00-0301:2016 Post-tensioning kits for prestressing of structures
EAD 160012-00-0301:2017 Headed reinforcement steel bars
EAD 160027:2016 Special filling products for post-tensioning kits
EAD 160129-00-0301:2020 Couplers for mechanical splices of reinforcing steel bars
EAD 200089-00-0302:2017 In-situ concrete slab permanent joint former
EAD 260002-00-0301:2016 Alkali resistant glass fibres containing zirconium dioxide for the use in concrete
EAD 260010-00-0301:2019 Fibres for concrete – steel fibres recovered from end-of-life tyres
EAD 260024-00-0301:2019 Polymer macro fibres reinforced with alkali resistant glass fibre for the use in concrete
EAD 260026-00-0301:2019 Waterproofing admixture for concrete
EAD 260067-00-0301:2020 Polymer macro fibres reinforced with basalt fibre for the use in concrete

General References

Publisher/Publication Number Title Year Link
American Concrete Institute ACI 400.1R-15 Guide for the Design and Construction of Structural Concrete Reinforced with Fiber-Reinforced Polymer (FRP) Bars 2015
American Concrete Institute ACI PRC-544.4-18 Guide to Design with Fiber-Reinforced Concrete 2018
Architectural Cladding Association Dawson S. Cast in Concrete: A Guide to the Design of Precast Concrete and Reconstructed Stone 2003
BRE BES 6001: Issue 4.0 Framework Standard for Responsible Sourcing 2022 BES_6001_V4-0.pdf
BRE BR501 The Green Guide to Specification, 4th Edition 2009 The Green Guide to Specification, 4th Edition(BR 501) DOWNLOAD
BRE Digest 330 Alkali-silica reaction in concrete 2004
BRE Special Digest 1 Concrete in aggressive ground 2005
Britpave Concrete Hardstanding Design Guidance 3rd Edition 2023
BRMCA Ready-mixed concrete: An essential sustainable construction material – locally available 2012 Essential_Ready_Mixed_Concrete_Feb_12.pdf
CARES Appendix PT2. The Supply and or Installation of Post-tensioning Systems in Concrete Structures 2021
CARES Appendix PT3 The Production and Supply of Prestressing Anchorages for Post-tensioning systems 2017
CARES Appendix PT4. The Supply and or Installation of Bar Post-tensioning Systems in Concrete Structures 2021
CARES Appendix PT7 Prestressing bar which ensures high tensile steel prestressing bars comply with BS 4486. 2021
CARES Appendix PT8. Wire and strand which ensures that high tensile prestressing wire and strand comply with BS 5896. 2021
CARES Appendix PT10 Prebagged grout complying with the requirements of BS EN 445, 446 and 447 2017
CARES The CARES Guide to Reinforcing Steels in 12 parts:
Part 7 Welded reinforcement fabric 2025 CARES Part 7
Part 8 Welding of reinforcing steels 2025 CARES Part 8
Part 9 Stainless Reinforcing Steels 2025 CARES Part 9
CCAA T57 Guide to off-form concrete finishes 2006
CCAA App for high wind concreting https://appomate.com.au/smart-concrete-ccaa/
CIRIA C147 Care and treatment of steel reinforcement and the protection of starter bars 1995
CIRIA C511 Controlled permeability formwork 2000
CIRIA C519 Action in the case of non-conformity of concrete structures 1999
CIRIA C558 Permanent formwork in construction 2001
CIRIA C568 Specifying, detailing and achieving cover to reinforcement 2001
CIRIA C766 Bamforth P. Control of cracking caused by restrained deformation in concrete 2018
CIRIA R135 Concreting deep lifts and large volume pours 1995
CIRIA R136 Formwork striking times: criteria, prediction and methods of assessment 1995
Climate Group ConcreteZero specification guidance 2025 Climate Group 25476 – ConcreteZero – Specifications Report.pdf
CONSTRUCT CS140 Guide to flat slab formwork and falsework 2003
Department of Finance and Personnel Technical Booklet D Building Regulations (Northern Ireland) 2012 Guidance: Structure 2012
fib Bulletin 40 FRP reinforcement in RC structures 2007
fib Bulletin 49 Corrosion protection of reinforcing steels 2009
fib Bulletin 75 Polymer-duct systems for internal bonded post-tensioning 2014
Health and Safety Executive Construction information sheet 56 Safe erection, use and dismantling of falsework 2003
ICE ICE Specification for Piling and Embedded Retaining Walls (SPERW), Third edition 2016
ICE Low Carbon Concrete Routemap 2022 low-carbon-concrete-routemap.pdf
ICE Reducing the risk of leaking substructure a clients’ guide. 2023 https://www.ice.org.uk/download-centre/reducing-the-risk-of-leaking-substructure
Innovate UK Universal classification scheme for embodied carbon of concrete 2023 https://www.arup.com/insights/embodied-carbon-classification-scheme-for-concrete/
MPA Factsheet 18 Embodied CO2e of UK cements 2025 FS_18_Embodied_CO2e.pdf
MPA Precast Code of Practice: The Safe Installation of Architectural and Structural Precast Concrete 2020 Arch-Health-Safety-Code-of-Practice-Final-051020.pdf
MPA Precast Code of Practice: The Safe Installation of Precast Concrete Flooring and Associated Components 2017 Flooring-CoP-Safe-Installation.pdf
MPA The Concrete Centre Visual Concrete 2015 Visual Concrete
MPA The Concrete Centre Reducing carbon and cost of reinforcement 2021 Reducing carbon and cost of reinforcement
MPA The Concrete Centre Specifying sustainable concrete: Aggregates 2025 Specifying Sustainable Concrete: Aggregates
MPA The Concrete Centre Specifying sustainable concrete: Using 56 day concrete strengths 2021 Specifying Sustainable Concrete: Using 56 Day Concrete Strengths
MPA The Concrete Centre Specifying Sustainable Concrete: Key considerations for specifying lower carbon concrete 2025 Specifying Sustainable Concrete: Key considerations for specifying lower carbon concrete
MPA The Concrete Centre Specifying sustainable concrete: BS8500 2025 Specifying Sustainable Concrete: BS 8500
MPA The Concrete Centre Material efficiency 2018 Material Efficiency
MPA The Concrete Centre Whole life carbon and buildings 2016 Whole-life Carbon and Buildings
MPA The Concrete Centre Specifying Sustainable Concrete: Supplementary cementitious materials 2024 Specifying Sustainable Concrete: Supplementary Cementitious Materials
MPA The Concrete Centre Specifying Sustainable Concrete: Reinforcement Specifying Sustainable Concrete: Reinforcement
MPA UK Concrete UK Concrete and Cement Industry Roadmap to Beyond Net Zero 2020 MPA-UKC-Roadmap-to-Beyond-Net-Zero_October-2020.pdf
NBS Approved Document A The Building Regulations 2010: Structure 2013
Post-tensioning Association GN01 Modifications and drilling of Post-tensioned Structures 2024 PTA-Guidance-Note_GN01_Mofications-and-Drilling-of-Post-tensioned-Structures.pdf
Post-tensioning Association GN03 Procurement of post-tensioned slabs Procurement of post-tensioned slabs
PTA/MPA The Concrete Centre Model Specification for the Design & Performance of Post-tensioned Concrete Floors 2017 Model Specification for the Design & Performance of Post-tensioned Concrete Floors
Scottish Government Building Standards Division Technical Handbook 2025 https://www.gov.scot/publications/building-standards-technical-handbook-2022-non-domestic/
The Concrete Society Concrete Advice 17 Achieving good quality as struck in-situ concrete surface finishes 2019
The Concrete Society Concrete Advice 20 Curing concrete 2016
The Concrete Society Concrete Advice 21 Dark discoloration on smooth formed concrete surfaces (mottling) 2016
The Concrete Society Concrete Advice 23 Large area pours for suspended slabs 2020
The Concrete Society Concrete Advice 25 Large volume concrete pours 2017
The Concrete Society Concrete Advice 34 High strength concrete columns and normal strength slabs 2018
The Concrete Society Concrete Advice 37 Mould release agents 2016
The Concrete Society Concrete Advice 43 Spacers and visual concrete 2016
The Concrete Society Concrete Advice 70 Vertical slipform surface finish 2022
The Concrete Society Concrete on Site 3 Formwork 2015
The Concrete Society CS030 Formwork – a guide to good practice. 3rd edition 2013
The Concrete Society CS123 Checklist for erecting and dismantling falsework 2014
The Concrete Society CS140 Guide to flat slab formwork and falsework 2003
The Concrete Society CS164 – Good Concrete Guide 8 Concrete practice: guidance on the practical aspects of concreting. 2016
The Concrete Society CS170 Visual Concrete: Finishes 2013
The Concrete Society CS171 Visual concrete – Planning and assessment 2013
The Concrete Society CS172 Visual Concrete: Control of blemishes 2013
The Concrete Society CS173 Visual Concrete: Weathering, stains and efflorescence 2013
The Concrete Society CS174 The influence of integral water-resisting admixtures on the durability of concrete 2013
The Concrete Society Technical Reports
The Concrete Society TR18 A guide to the selection of admixtures for concrete 2002
The Concrete Society TR22 Non-structural cracks in concrete 2010
The Concrete Society TR34 Concrete industrial ground floors – a guide to design and construction. 4th edition 2018
The Concrete Society TR43 Post-tensioned concrete floors – design handbook 2005
The Concrete Society TR51 Guidance on the use of stainless steel reinforcement 1998
The Concrete Society TR52 Plain formed concrete finishes 2015
The Concrete Society TR61: part 1 Enhancing reinforced concrete durability: Guidance on selecting measures for minimising the risk of corrosion of reinforcement in concrete 2004
The Concrete Society TR61: part 2 Enhancing reinforced concrete durability: Guidance on selecting measures for minimising the risk of corrosion of reinforcement in concrete: Part 2 Supplementary technical reports 2004
The Concrete Society TR61: part 3 Enhancing reinforced concrete durability: Guidance on selecting measures for minimising the risk of corrosion of reinforcement in concrete: Part 3 Supplementary data reports 2004
The Concrete Society TR63 Guidance for the design of steel-fibre-reinforced concrete 2007
The Concrete Society TR65 Guidance on the use of macro-synthetic-fibre-reinforced concrete 2007
The Concrete Society TR66 External in-situ concrete paving 2009
The Concrete Society TR67 Movement, restraint and cracking in concrete structures 2008
The Concrete Society TR69 Repair of concrete structures with reference to BS EN 1504 2009
The Concrete Society TR72 Durable post-tensioned concrete structures 2010
The Concrete Society TR75 Composite concrete slabs using steel decking: guidance on construction and associated design considerations 2016
The Institution of Structural Engineers Structural use of fibre polymer composites 2023
The Institution of Structural Engineers The efficient use of GGBS in reducing global emissions 2023 https://www.istructe.org/resources/guidance/efficient-use-of-ggbs-in-reducing-global-emissions/
The Structural Engineer Volume 99, Issue 10 Cover to reinforcement – getting it right: product performance requirements (Chris Shaw) 2021
The Structural Engineer Volume 99, Issue 11, Cover to reinforcement – getting it right: use of spacers and chairs, and tying of reinforcement (Chris Shaw) 2021
Walter de Gruyter GmgH Bennett D. The Art of precast concrete 2005
Welsh Government Approved Document A The Building Regulations 2010: Structure 2017 170403building-regs-approved-document-a-structure-en.pdf

Section 0.2 Scope

The NSCS has the same scope as BS EN 13670 for Building Structures. It provides a framework for providing additional information on lightweight concrete, use of fibres, special designs, the integration of concrete products into a design and defining responsibilities between the parties. It is intended to be used with the ICE Specification for Piling and embedded Retaining Walls for foundation structures – SPERW.

The NSCS is laid out in terms of processes, and it uses the same sequence as BS EN 13670. European and British Standards are referenced rather than reproduced within the document.

The NSCS covers requirements for the construction of concrete building structures of in-situ concrete, precast concrete, and hybrid concrete systems. It is intended for use with structures designed to BS EN 1992, although it can be used when other design standards are used. Where the NSCS is to be used for structures in extreme environments, those produced by specialist construction techniques or those of a specialist design nature, the Project Specification should include the particular requirements where appropriate.

The NSCS is written with safety in mind but does not specify Health and Safety requirements as they are legal regulations that apply to all construction and are inherent within this specification. In the UK designers must comply with the CDM Regulations. This requires designers to assess risks and design them out where possible, to do this they must understand the process required to achieve each aspect of any design – the weight of units to handled, the implications of creating any special finish, etc.

Where the NSCS refers to specifications, standards or regulations this shall be to the latest edition. 

Specific obligations are placed on the Constructor, the Client and the Engineer. In some cases these will be different organisations; sometimes any or all will be represented by the same organisation. However, their responsibilities remain as required under the Contract.

The NSCS Project Clauses are to be read in conjunction with these Standard clauses and outline project information specific to a particular project that is additional to the requirements of Standard Clauses.

The NSCS Project clauses cover the exchange of information necessary between the Client  and Constructor at tender stage and contract stage. Completion of the Project clauses is intended to be as required for the stage for which it is being used, i.e. at time of tender or contract commencement.

The NSCS Project clauses allow the Engineer responsible for the design the freedom to incorporate specific text to vary and add to the Standard clauses at tender. Likewise the Constructor can propose variations when returning the tender. It is emphasised that the Standard clauses have been produced as a non-prescriptive specification to meet the standards required by BS EN 13670 and therefore any amendments through the Project clauses should be as few as possible.

The Standard clauses cannot be altered; they can only be amended by using the Project clause P4.1.1.1.

This allows those receiving the specification, Principal Contractor, Constructor, Concrete Producer, Precast Concrete Manufacturer, Specialist designer etc. to be clear about project changes and requirements.

The pro-forma layout of NSCS Project clauses acts as an aide memoire to the disclosure of relevant information for most types of project.

NSCS Guidance provides background information on the content and explains why certain clauses have been adopted. NSCS Guidance is designed to be ‘dipped into’, and read with the relevant Standard and Project clauses; as a result there is some intentional duplication.

Section 1 Information

P1.1 Client Project Contacts

Client Project Contacts

Project name[Cover Field Text Here]
Project ref[Cover Field Text Here]
Address[Text Input Here]

Client

Name[Cover Field Text Here]
Address[Text Input Here]
Contact Name[Text Input Here]
Telephone[Text Input Here]Email[Text Input Here]

Principal Contractor

Name[Cover Field Text Here]
Address[Text Input Here]
Contact Name[Text Input Here]
Telephone[Text Input Here]Email[Text Input Here]

Engineer

Name[Cover Field Text Here]
Address[Text Input Here]
Contact Name[Text Input Here]
Telephone[Text Input Here]Email[Text Input Here]

Contract administrator – CA

Name[Cover Field Text Here]
Address[Text Input Here]
Contact Name[Text Input Here]
Telephone[Text Input Here]Email[Text Input Here]

Other named parties to the contract

Name[Text Input Here]
Address[Text Input Here]
Contact Name[Text Input Here]
Telephone[Text Input Here]Email[Text Input Here]

P1.2 Constructor Project Contacts

Constructor

Name[Text Input Here]
Address[Text Input Here]
Contact Name[Text Input Here]
Telephone[Text Input Here]Email[Text Input Here]

Designer

Name[Text Input Here]
Contact Name[Text Input Here]
Telephone[Text Input Here]Email[Text Input Here]

Designated Individual / Temporary works – Co-ordinator

Name[Text Input Here]
Contact Name[Text Input Here]
Telephone[Text Input Here]Email[Text Input Here]

Proposed Producer

Name[Text Input Here]
Address[Text Input Here]
Contact Name[Text Input Here]
Telephone[Text Input Here]Email[Text Input Here]

Proposed specialist contractor for prestressed concrete

Name[Text Input Here]
Contact Name[Text Input Here]
Telephone[Text Input Here]Email[Text Input Here]

Proposed precast concrete manufacturer

Name[Text Input Here]
Contact Name[Text Input Here]
Telephone[Text Input Here]Email[Text Input Here]

Other Specialists to be used by the Constructor

Name[Text Input Here]
Contact Name[Text Input Here]
Telephone[Text Input Here]Email[Text Input Here]

1.3 Basic Requirements

The specification for the structure shall be the National Structural Concrete Specification for Building Construction – NSCS.

The NSCS Project Specification is provided by the Client at tender and identifies the appropriate information specific to the structure which includes the NSCS Standard Clauses. Standard Specification Clauses may be modified by information given in the Project Clauses.

P1.4 Description of the project works

[Text Input Here]

P1.5 Construction planning requirements

The Constructor should notify the CA if any discrepancy is identified between the Contract Documents and the Specification.

Where details of the site conditions are provided, such as underground services, overhead cables, adjacent buildings and site obstructions, they are given to assist the Constructor in their tender stage planning. The Constructor should always confirm the accuracy of this information when on site, before starting work.

General

[Text Input Here]

Positions of the Reference Line, as defined in BS EN 13670; datum level and setting-out lines, width and level of access, level of the prepared working area for site traffic, cranes and pumps, and areas available for storage and site accommodation are shown on drawing numbers.

[Text Input Here]

Details of underground services, overhead cables, adjacent buildings, site obstructions or other constraints on the Constructor.

[Text Input Here]

Availability of site services and any prearranged procedures for sole or shared use.

[Text Input Here]

Factors affecting construction sequence, including working restrictions on time or special nuisance, including noise; or other aspects that may create an unusual hazard.

[Text Input Here]

Special requirements for temporary propping.

[Text Input Here]

Restrictions on dimensions and/or weights of units to be delivered to site.

[Text Input Here]

Interface requirements / restrictions between the works and following trades.

[Text Input Here]

Special requirements for headroom

[Text Input Here]

A programme showing clearly and phased requirements and the earliest and latest release dates of work to following trades or to the Client is shown on document reference:

[Text Input Here]

Access will be made available to the Constructor on

[Text Input Here]

Environmental factors relating to achievement of Considerate Contractors or Site Waste Management requirements

[Text Input Here]

Section 2 Design

P2.1 General

The design has been carried out in accordance with BS EN 1990, BS EN 1991 and BS EN 1992. Any design by the Constructor is to be carried out in accordance with these codes and the design data given in this specification.

[Text Input Here]

P2.2 Loading

Loading
All given in kN/m2 unless noted
Floor Load[Text Input Here]
ImposedGeneral[Text Input Here]Dead LoadSelf-weight[Text Input Here]
Partitions[Text Input Here]Partitions[Text Input Here]
Flooring[Text Input Here]
Screed[Text Input Here]
Services[Text Input Here]
Ceiling[Text Input Here]
Total[Text Input Here]Total[Text Input Here]

Cladding Load

[Text Input Here][Text Input Here]

Wind Load

[Text Input Here][Text Input Here]

Other Load

[Text Input Here][Text Input Here]

P2.3 Other design data

Design Life - years

[Text Input Here][Text Input Here]

Fire rating - hours

[Text Input Here][Text Input Here]

Exposure class

[Text Input Here][Text Input Here]

Maintenance/replacement assumptions

[Text Input Here][Text Input Here]

Other

[Text Input Here][Text Input Here]

P2.4 Special requirements for composite structures

[Text Input Here]

P2.5 Drawings and calculations

ItemTypePrepared byInformation IssueAcceptance IssueConstruction Issue
Period before construction - weeks
ProjectProjectProject
General arrangement drawingsRCCA[Text Input Here][Text Input Here]
PSCCA[Text Input Here][Text Input Here]
PrecastCA[Text Input Here][Text Input Here]
Design Information drawingsRCCA[Text Input Here][Text Input Here]
PSCCA[Text Input Here][Text Input Here]
PrecastCA[Text Input Here][Text Input Here]
Construction sequence infoAllCA[Text Input Here][Text Input Here]
Design calculationsRC[Text Input Here][Text Input Here][Text Input Here]
PSC[Text Input Here][Text Input Here][Text Input Here]
PCECA[Text Input Here][Text Input Here]
BPCCA[Text Input Here][Text Input Here]
PPCManufacturer[Text Input Here][Text Input Here]
Specialist drawingsRC[Text Input Here][Text Input Here][Text Input Here]
PSC[Text Input Here][Text Input Here][Text Input Here]
PCECA[Text Input Here][Text Input Here]
BPCCA[Text Input Here][Text Input Here]
[Text Input Here]PPCManufacturer[Text Input Here][Text Input Here]
Builders' work informationAllCA[Text Input Here][Text Input Here]
Reinforcement drawings and schedulesRCCA[Text Input Here]
Coordinated Builders' work drawingsAllCA[Text Input Here][Text Input Here]
Temporary works information; including backproppingAll[Text Input Here][Text Input Here][Text Input Here]
As built drawingsAllCA[Text Input Here]
Types of construction:
RC: Reinforced concrete PSC: Prestressed concrete PCE: Precast concrete elements
BPC: Purpose made, bespoke, precast concrete units to meet requirements in specification
PPC: Precast proprietary concrete products in accordance with product standards

P2.6 Details of Constructor designed structure

[Text Input Here]

P2.7 Constructor proposed design & variations

[Text Input Here]

Section 3 Definitions

The following definitions, in addition to those given in BS EN 13670, apply for the purpose of this Specification.

3.1 Agreement, acceptance

When by or of the CA, agreement or acceptance shall have the following limitations.

3.1.1 Samples

When given in respect of samples of materials, execution or proposals for methods of construction submitted in accordance with this Specification, shall not be interpreted as denoting any degree of satisfaction with the materials used in, or the execution of the Works.

3.1.2 Documents

When given in respect of drawings, documents, or schemes called for by the Specification or proposed by the Constructor, is only for conformity with the design concept and design information given in the Contract Documents or contained in subsequent instructions from the CA.

Acceptance or agreement shall not diminish or relieve the obligations of the Constructor under the Contract.

3.2 BIM execution plan: BEP

Plan that explains how the information management aspects of the appointment will be carried out by the Constructor.

3.3 Client

Organization or person for which/whom a construction project is carried out.

3.4 Constructor

The specialist concrete firm constructing the works.

3.5 Contract Administrator: CA

The named individual or company, engaged to act for and on behalf of the Client for the purpose of accepting proposals from the Constructor, issuing technical information to the Constructor and monitoring the work of the Constructor.

3.6 Design calculations

The calculations produced generally by the Engineer. For some specialist work they may be produced by a specialist designer working for the Constructor.

3.7 Drawings models and schedules

3.7.1 General arrangement drawings: GAs

Plans and sections indicating the layout and dimensions of each floor of the Works. The drawings will be in sufficient detail to allow the formwork to be constructed and will show or reference all inserts or cast­in items and holes. Drawings should indicate the locations of concrete grades and finishes.

3.7.2 Design information drawings

Drawings prepared to show the design information required to enable reinforcement detail drawings to be produced.

3.7.3 Specialist drawings

Detailed and dimensioned general arrangement drawings by Manufacturers or Suppliers for the layout of precast planks, waterbars, membranes, inserts and mould drawings for special precast units including prestressed, etc.

P3.7.4 Post-tensioned concrete drawings

Fully dimensioned drawings, plans and cross-sections of tendons and anchorage layouts indicating tendon profiles at regular intervals along each length, support details, stressing sequences etc.

Stressing end, dead end anchorages, and any ordinary reinforcement sizes and locations required to supplement the post-tensioning design and bursting reinforcement at anchorages to suit anchor type and layout, shall be clearly defined.

3.7.5 Reinforcement detail drawings

Drawings prepared to show the layout of the various types of reinforcement used in the construction of the Works. They shall be prepared in accordance with the requirements of BS EN 1992 and the Standard method of detailing structural concrete – A manual for best practice – IStructE.

3.7.6 Reinforcement schedules

Schedules prepared to show the details of each bar to be cast into the concrete. They shall be prepared in accordance with BS 8666.

3.7.7 Construction sequence information

Drawings, sketches or other information, prepared by the CA, indicating any special requirements or methods, which the Constructor must consider in the preparation of their temporary works in order to erect the Works in a safe manner.

3.7.8 Temporary works and erection drawings

Drawings prepared to show necessary falsework, formwork and propping that are employed to construct the Works in a safe manner.

3.7.9 Builders' work drawings

Drawings prepared to show coordinated builders’ work – holes, cast-in services and fixings, etc.

3.7.10 As-built drawings

Drawings to indicate what was built.

3.8 Engineer

The individual or organisation responsible for the overall design of the Structure.

3.9 Examples, Benchmarks and Mock ups

3.9.1 Examples

An area of publicly accessible concrete finish from previous projects, including those listed on MPA The Concrete Centre website, or the CONSTRUCT Example panels that demonstrate the project expectations for:

  • standard of plain formed finishes
  • standard of ordinary formed finishes
  • special formed finishes

3.9.2 Mock Up

A bespoke project specific physical trial construction.

3.9.3 Project Physical Benchmark

A part of the structure built in advance of the area where the finish is required that defines the standard expected for the project.

3.10 Manufacturer

For pre-cast concrete the individual or organisation that supplies factory produced precast concrete; including elements, products built in accordance with the CA’s supplied design and drawings, and proprietary products designed by them to meet the design brief given by the CA.

3.11 Prestressed concrete

Concrete that is subjected to pre-tensioning or post-tensioning.

3.12 Producer

The organisation supplying concrete for site construction.

3.13 Project specification

National structural concrete specification for building construction – NSCS Standard Clauses and NSCS Project Clauses.

3.14 Site

The designated place where the Constructor will construct the Works.

3.15 Specialist designer

Anyone working for the Constructor or a Manufacturer who completes the detail design of any part of the structure to meet the requirements set out on the GAs and design information drawings.

3.16 Temporary Works Coordinator

The named individual, or individuals, employed by the Constructor responsible for coordinating the temporary works for construction of the works.

3.17 The Works

Structure to be built by the Constructor.

3.18 Waterproofing Specialist

Specialist designer who co-ordinates the detailing for water-resistant concrete in accordance with BS 8102.

Section 4 Execution management

4.1 General requirements

4.1.1 Standards

Execution shall be in accordance with BS EN 13670 as supplemented by the Project Specification and all statutory requirements.

Where there is a difference between the requirements of BS EN 13670 and the Project Specification, the Project Specification takes precedence.

P4.1.1.1 Project requirements

Enter variations from NSCS Standard Clauses

Client Requirements
N: new D: deleted
M: modified
Standard specification clause ref.
Description
[Text Input Here][Text Input Here][Text Input Here]
[Text Input Here][Text Input Here][Text Input Here]
Constructor / Contractor Proposals
N: new D: deleted
M: modified
Standard specificationDescription
[Text Input Here][Text Input Here][Text Input Here]
[Text Input Here][Text Input Here][Text Input Here]

4.1.2 Materials

4.1.2.1 General

All materials used in the structure shall comply with the Project Specification and current versions of standards referred to therein. The CA may specify samples for testing and the Constructor shall arrange for such samples to be supplied, identified, stored and tested and the results delivered to the CA in accordance with the relevant standards and the Project Specification requirements.

P4.1.2.2 Proprietary products and materials

These shall be used in accordance with the manufacturer’s written instructions and relevant UK and/or European Product Standards where available.

Materials not permitted

[Text Input Here]

Materials requiring special consideration

[Text Input Here]

Items supplied by the Client

[Text Input Here]

Material to specified under Constructor specified supply

[Text Input Here]

Alternative materials, or material sources proposed by the Constructor:

[Text Input Here]

4.1.2.3 Third- party inspections

Allow reasonable access to the site for technical inspection by third parties at all times.

4.1.2.4 Water-resisting construction

Where water-resisting construction is specified, submit to the CA for agreement: details of the materials used and the execution, which are to be in accordance with BS 8102; and written confirmation from the supplier of the water-resisting materials that they will not be adversely affected by the proposed environment, concrete, curing and release agents, placing methods, joints, finishes, reinforcement and its support details, or loads.

P4.1.2.5

The following materials will be used for water-resisting construction as shown on the construction drawings/ The Constructor shall provide details of the following materials for all water-resisting construction:

LocationDetailWaterstopsSeparation membranesJoint fillers
Manufacturer[Text Input Here][Text Input Here][Text Input Here]
Material[Text Input Here][Text Input Here][Text Input Here]
Slabs: horizontal construction jointsType[Text Input Here][Text Input Here][Text Input Here]
Slabs: horizontal movement jointsType[Text Input Here][Text Input Here][Text Input Here]
Walls: horizontal slab/wall junctionsType[Text Input Here][Text Input Here][Text Input Here]
Walls: vertical construction jointsType[Text Input Here][Text Input Here][Text Input Here]
Walls: vertical movement jointsType[Text Input Here][Text Input Here][Text Input Here]

4.1.3 Supervisors and operatives

All supervisors and operatives shall have the appropriate knowledge, training and experience for carrying out their tasks on site.

4.2 Responsible Sourcing & Use

All materials used in the construction for both temporary and permanent works should be responsibly sourced to a sector certification scheme in accordance with BS8902, with appropriate third-party certification against BES6001 whenever this is available; all material should be used sustainably with waste minimised.

P4.2.1 Responsible sourcing

[Text Input Here]

4.3 Documentation

P4.3.1 Quality plan

Operate an agreed quality management system, which shall be accessible for audit.
The Constructor shall prepare a quality plan for the project; and give this the CA for acceptance at least five working days before the Works start.

P4.3.1.1 Management Standards

The Constructor shall operate a quality management system to BS EN ISO 9001 and an environmental management system to BS EN ISO 14001; with appropriate third-party certification.

4.3.2 Execution documentation

Produce the documents as required and provide to the CA at the time stated in clause P4.3.2.1.

P4.3.2.1 Execution documentation

An Information required schedule based on the construction programme and this specification to be issued to the CA within

[Text Input Here]

working days of the Constructor being appointed.

Constructors document reference:

[Text Input Here]

The following documentation is required:

InformationNumber of working days before construction with updates as requested unless noted
Constructor's Quality Assurance Certification[Text Input Here]
Detailed construction programme[Text Input Here]
Falsework and formwork:design[Text Input Here]
pre- concreting cleanliness[Text Input Here]
EPD / responsible sourcing documentation [Text Input Here]
Reinforcementsource and supplier[Text Input Here]
Certification[Text Input Here]
pre-concreting location[Text Input Here]
pre- concreting locationAs requested[Text Input Here]
EPD / responsible sourcing documentation [Text Input Here]
Spacers[Text Input Here]
Couplerssource and supplier[Text Input Here]
Certification[Text Input Here]
Continuity stripssource and supplier[Text Input Here]
Certification[Text Input Here]
Post-tensioning workCertification[Text Input Here]
Specific quality plan[Text Input Here]
Other information[Text Input Here]
EPD / responsible sourcing documentation[Text Input Here]
Concreteready-mix plant details[Text Input Here]
certificationready-mix Producers'[Text Input Here]
delivery ticket[Text Input Here]
EPD / responsible sourcing documentation[Text Input Here]
Concreting: method statement and pour sequence for each section of the work[Text Input Here]
Precast concrete[Text Input Here]
As-built geometry: setting out and dimensions[Text Input Here]
As-built geometry: reinforcement cover[Text Input Here]

P4.3.2.2 Approvals timing

The timings given in NSCS Standard Specification apply to all approvals except as noted below.

Specification clause ref.ItemRequirements
Before or after, as appropriate
Working days unless stated
4.1.4.1Material test results[Text Input Here]
4.3.1Quality plan[Text Input Here]
4.4.3Notice to CA for inspection:
Before each concrete pour.
[Text Input Here]
4.4.3Before prestressing work starts[Text Input Here]
4.4.3Before covering up or backfilling[Text Input Here]
4.4.3For water-resisting construction to allow joint inspections[Text Input Here]
4.4.4Response by CA to request for modifications[Text Input Here]
4.4.7Copies of test results[Text Input Here]
4.4.8Proposal and response time for work rectification[Text Input Here]
6.3.1Notice to CA for site changes to reinforcement[Text Input Here]
7.2.1.5Extension calculations for post-tensioning tendons[Text Input Here]
7.4.1.1Notice to CA for site changes to post -tensioning tendons[Text Input Here]
7.5.1Grouting records[Text Input Here]
8.1.2.2Concrete non-conformity[Text Input Here]
8.2.1.4Premature cessation of a pour[Text Input Here]
9.1.3Precast connection details[Text Input Here]
9.6.3Precast erection specification and work programme[Text Input Here]
OtherCutting and drilling precast elements[Text Input Here]

P4.3.2.3 Approvals timing - visual concrete

The Constructor is to provide details of project(s) that demonstrates their ability to produce the finishes set out in the Visual Concrete Report.

The Constructor is to arrange visit(s) to 

[Text Input Here]

projects that demonstrate where they have constructed concrete finishes similar to those required as set out in the Visual Concrete Report during the tender period.

4.3.3 Information coordination and availability

4.3.3.1 NSCS Project Specification

When the Project Specification is revised all changes must be clearly identified.

4.3.3.2 Availability

Copies of all documents required for the construction of the structure, including all inspection reports, shall be available for review on site during the contract period.

4.3.3.3 Coordination

The Constructor shall ensure that the coordinated information they prepare, as required by the Project Specification Tables P1.2, P4.1.1.1, P4.3.2.1, P4.3.2.2, P8.1, & P9.8 and clauses P2.5, P2.6, P2.7, P4.1.2.2 & P8.2.1.1 is submitted to the CA for agreement in accordance with the Project Specification requirements.

4.3.3.4 BEP

The Constructor shall contribute to the project BIM model exchange, change control and coordination procedure as outlined in the BEP.

4.3.3.5 Register

Where a project does not use a common data environment as set out in the BEP the Constructor shall maintain a register of all documents they receive and issue, identifying the source of the document, revision symbol and date received or issued by the Constructor.

4.3.3.6 Circulation

The dates for issue of documents shall be in accordance with the Project Clause P2.5, agreed with the CA and recorded in the quality plan.

4.3.4 BIM Models

All models and shared data must be in accordance with the project BEP Where information on a model is updated the alteration should be clearly identifiable.

4.3.5 Drawings and reinforcement schedules

4.3.5.1 Standards

To be in accordance with BS EN ISO 4157. Revisions, with the date made, and status shall be clearly shown. A circle or cloud around drawing revisions should identify the changes made for the latest revision symbol. The changes should be described in notes on the drawing corresponding to the latest revision symbol.

4.3.5.2 Production

Drawings are to be produced as detailed in the table given in clause P2.5. Where the drawings are to be prepared by a manufacturer of precast concrete products, or a specialist post­ tensioning contractor, the Constructor is to ensure that the drawings are issued to the CA in accordance with the requirements of Project Clause P2.5 and the project BIM execution plan.

4.3.5.3 Reinforcement schedules

The CA and Constructor shall each be responsible for the accuracy of any schedules that they produce.

4.3.5.4 Builders' work drawings

Where the Constructor is to produce coordinated builders’ work drawings the CA shall provide the required information in accordance with an agreed programme.

P4.3.5.5 As-built drawings and models

The Constructor is to produce As-built drawings and models; these are to be issued not more than three months after the structure is complete.

4.3.6 Construction planning - temporary works

The CA’s construction sequence information must be considered in the preparation of the Constructors’ temporary works drawings showing all stability requirements during erection.

Temporary conditions and loading on partially constructed permanent structure must be assessed by the Constructor.

Method statements for erection and dismantling of temporary works including all details of propping/ re-propping and backpropping through the structure are to be prepared by the Constructor and agreed with the CA.

4.4 Quality management

4.4.1 Execution class

The works are to be built in accordance with Execution Class 2, other than for post-tensioned construction where Class 3 is to be used, unless otherwise specified in clause P4.4.1.1.

P4.4.1.1 Execution Class

The following parts of the structure are to be constructed in accordance with execution Class 3.

[Text Input Here]

4.4.2 Setting out

Set out the structure to the given setting out information.

4.4.3 Inspection

In addition to the Constructor’s inspection of the materials and execution in accordance with BS EN 13670 the Constructor is to give reasonable notice, as given in P4.3.2.2, to allow inspection by the CA at the following stages:

  • Before each concrete pour.
  • Before prestressing work starts.
  • Before covering up or backfilling.
  • For water-resisting construction to allow inspection jointly with Constructor as Cl. 8.4.2 of this Specification

P4.4.3.1 Inspection

Items not defined in table 1 of BS EN 13670:2009 shall be inspected as follows.

[Text Input Here]

Additional inspection to that described in table 3 of BS EN 13670:2009 shall be as follows.

[Text Input Here]

Additional third-party inspection
Carried out by

[Text Input Here]

Is required of the following parts of the structure.

[Text Input Here]

4.4.4 Modifications

Obtain the written agreement of the CA to any modifications of this Specification before any work is started.

4.4.5 Storage

All materials shall be stored in an agreed manner that prevents damage or degradation and is in accordance with all manufacturers’ requirements.

4.4.6 Acceptance procedure

The CA shall comment on all information supplied within five working days of receipt. Acceptance or agreement by the CA shall have no effect unless given in writing.

4.4.7 Testing

Supply electronic copies of all test reports to the CA as soon as they are available.

4.4.8 Action in the event of a non-conformity

  • Any test or inspection reports that show that any part of the structure does not meet the specified criteria shall be issued to the CA, as soon as they are available.
  • Provide proposals for dealing with the non-conformity to the CA within five working days of reporting the issue.
  • A course of action shall be agreed within a further five working days. Where the Constructor is responsible for a non-conformity the cost of all additional testing and remedial works shall be at the Constructor’s expense.

P4.4.9 Protection

The following special protection is required.

[Text Input Here]

Section 5 Falsework and formwork

5.1 Standards

Design and construction should be in accordance with the following where applicable:

  • BS 5975-1: Temporary works. Management procedures for the control of temporary works – code of practice
  • BS 5975-2: Temporary works. Falsework: Design and implementation – code of practice
  • Formwork: a guide to good practice: Concrete Society Publication CS030 2012
  • Guide to flat slab falsework and formwork: Concrete Society publication on behalf of CONSTRUCT, CS140, Pallet, 2003.
  • Formwork striking times – Criteria, prediction and method of assessment: CIRIA Report 136, Harrison, 1995
  • BS EN 1990 Eurocode Basis of Structural Design & BS EN 1991 Actions on Structures
  • BS EN 12812 Falsework – Performance requirements and general design

5.2 Materials

Permanent formwork may be used subject to the agreement of the CA.

All formwork and falsework materials should be sustainably sourced with appropriate third-party certification whenever this is available; and shall be used sustainably. Where practicable provide an EPD or equivalent confirmation of the global warming potential of the formwork in kgC02e/kg.

Formwork should be prefabricated where practical and handled with care to maximise reuse and minimise wastage.

Release agents shall be chosen to suit the method of construction, and the finish required. They shall not be adversely affected by the weather.

5.3 Formwork use

5.3.1 Ground support

Concrete shall not be cast directly against existing construction or faces of excavations without prior agreement of the CA. Where structural concrete relies on permanent or temporary support from the ground, ensure that the support is firm enough for concreting operations.

5.3.2 Cleanliness

Formwork shall be clear of all debris, water, snow and ice before concrete is placed.

5.4 Block outs and cast-in items

Set out and fix all cast-in items shown or referenced on the drawings. Any clashes between holes, cast in items and reinforcement shall be resolved to the agreement of the CA before any concrete is placed.
Block out items shall be cleared out after concreting.

5.5 Formwork ties

Through ties may be used to support vertical faces of formwork other than in water-resisting construction or as agreed with the CA.

No ferrous metals shall be left in the concrete cover zone when formwork has been struck.

Any formwork tie holes left exposed to view in the faces of the concrete shall be filled to the agreement of the CA.

5.6 Loading, striking and backpropping

5.6.1 Temporary construction loads

Ensure the structure is not subjected to temporary loads during construction that will cause distress, taking account of the maturity of the concrete at the time of loading.

5.6.2 Striking

Falsework and formwork shall be struck at a time determined by the Constructor to comply with this Specification.
Formwork shall be removed carefully so as to avoid damage to the concrete surface.

5.6.3 Backdropping

The exact sequence of propping/re-propping and backpropping through the structure, set out in a method statement by the Constructor, shall be agreed with the CA in advance, and should have no damaging effect on the Permanent Works.

5.6.4 Cold weather concreting

Any special requirements for the formwork design, including any use of heated forms or changes in design formwork pressure for concreting in cold weather, shall be agreed with the CA in advance.

5.7 Construction joints and pour sizes

5.7.1 Geometry

Produce drawings showing the lay out of construction joints and agree their location with the CA. Joints are to be positioned so as not to cause the structure any distress.

The pour sizes proposed and justified by calculation by the Constructor, shall be agreed with the CA in advance; if not they shall be as shown below.

ConstructionMaximum area: m^2Maximum dimension: m
Water-resisting walls255
Water-resisting slabs10010
Slabs with major restraint at both ends10013
Slabs with major restraint at one end only25020
Slabs with little restraint in any direction50030
Walls4010

5.7.2 Joint preparation

Use appropriate method of creating good construction joint surfaces, so scabbling using hand tools should not be required.

P5.7.3 Deflection Allowances

To be used in calculating formwork pre-camber.

[Text Input Here]

5.8 Water-resisting construction

5.8.1 Waterstops

Use waterstops in all construction joints and movement joints in accordance with the manufacturer’s written instructions. Obtain the agreement of the CA for the methods to be used to maintain them in their correct locations and prevent damage while concrete is being placed and during or after removal of the formwork. Hydrophilic water stops should be protected from premature swelling under wet conditions.

Submit for agreement with the CA drawings indicating the positions of joints and details of waterstops to be used. Details shall include schedules of all junction pieces, which shall be purpose made, and isometric layouts of waterstops.

Where centre section waterstops are proposed, submit to the CA for agreement the methods to be used to ensure full compaction of the concrete around the waterstop.

5.8.2 Formwork ties

Formwork ties used shall be of a type to maintain water resistance of the construction.

Where a method of fixing formwork requires holes through the concrete section, details shall be agreed with the CA.

Section 6 Reinforcement

6.1 Ferrous Reinforcement

6.1.1 General

6.1.1.1 Standards

All stainless steel reinforcement shall conform to BS 6744.

All other reinforcement shall conform to BS 4449, BS 4482 or BS 4483 as appropriate.

All reinforcement shall be cut and bent in accordance with BS 8666.

All reinforcement should be sustainably sourced with appropriate third-party certification whenever this is available; and shall be used sustainably. Provide a site, product and manufacturing route specific EPD conforming to BS EN 15804 or equivalent confirmation of the global warming potential (total covering modules A1, A2 and A3) of the reinforcement in kgC02e/kg.

P6.1.1.2 Reinforcement Type & Grade

Reinforcement in accordance with BS 4449 or BS 6744 grade 500 shall be used except in the following locations.

[Text Input Here]

Stainless steel reinforcement shall be used in the following locations.

[Text Input Here]

Galvanised steel reinforcement shall be used in the following locations.

[Text Input Here]

6.1.1.3 Certification - supplier

Unless agreed otherwise by the CA, all reinforcement shall be obtained from firms holding a valid UKAS approved product approval certification for the production and supply of steel reinforcement against the requirements of BS 8666. A supplier Certificate of Approval reference shall be stated on all documentation.

6.1.1.4 Certification – cutting and bending

Unless agreed otherwise by the CA, all cutting and bending operations shall be conducted by firms holding valid UKAS approved product approval certification for the processing and supply of steel reinforcement against the requirements of BS 8666. A supplier Certificate of Approval reference shall be stated on all documentation.

6.1.2 Spacers

Supply, detail and fix all spacers – chairs, blocks, supports and devices of a special nature required to hold the reinforcement in the correct position during concreting. The materials and workmanship shall be in accordance with BS 7973: Spacers and chairs for steel reinforcement and their specification. Ensure that the spacers have the required performance characteristics. The type and layout of the spacers should be agreed with the CA before any work is started.

6.1.3 Continuity strips

6.1.3.1 Supply

Proprietary continuity strips can be used subject to agreement by the CA.

6.1.3.2 Quality

Unless otherwise agreed by the CA, the continuity strip manufacturers shall hold:

  • a valid CARES Technical Approval scheme Certificate of Approval to TA2 Quality and Operations Schedule for the Technical Approval of Reinforcement Continuity Systems or fully equivalent scheme.
  • a valid CARES Technical Approval scheme Certificate of Approval, or fully equivalent scheme.
  • a valid CARES or fully equivalent ISO 9001 Certificate of Approval.

6.1.4 Couplers

6.1.4.1 Supply

Details of the source and suppliers shall be forwarded to the CA for agreement. Only one coupler type is to be used unless otherwise agreed by the CA. Couplers to comply with BS 8597.

6.1.4.2 Quality

Unless otherwise agreed by the CA, the mechanical coupler manufacturers shall hold a valid UKAS approved product approval certification for the manufacture and supply of coupler systems in accordance with BS 8597 and the approval bodies requirements. 

Reinforcing bars shall be adequately and appropriately prepared by the supplier to receive the agreed couplers. Unless agreed otherwise by the CA, the bar end preparation shall be conducted by firms holding a valid UKAS approved certificate for the fabrication and supply of coupler systems in accordance with BS 8597 and the approval bodies requirements.

6.1.4.3 Execution

Couplers and threads must be inspected for damage before connecting. Coupler connection must be tightened or torqued in accordance with the manufacturer’s requirements. Where on-site repair coupler systems are used the requirements of 6.1.4.2 apply and the Constructor shall ensure that the installation is as the manufacturers and approval bodies’ installation instructions.

P6.1.4.4 Coupler Details

Anchorages and couplers shall be

[Text Input Here]

6.1.5 Punching shear reinforcement systems

6.1.5.1 Supply

Details of the source and suppliers shall be forwarded to the CA for agreement.

6.1.5.2 Quality

Unless otherwise agreed by the CA, the punching shear reinforcement system manufacturers shall hold:

  • a valid CARES Technical Approval scheme Certificate of Approval, or fully equivalent scheme.
  • a valid CARES or fully equivalent ISO 9001 Certificate of Approval.

6.1.6 Fibre reinforcement

Unless fully described in Clause P6.1.6.1, details of the proposed fibres, dosage, source and suppliers shall be forwarded to the CA for agreement.

P6.1.6.1 Ferrous fibres

shall be used as follows

Types of fibreLocation and dosage
[Text Input Here][Text Input Here]

6.2 Non-Ferrous Reinforcement

All reinforcement should be sustainably sourced; provide an EPD or equivalent confirmation of the global warming potential of the reinforcement in kgC02e/kg.

6.2.1 Bassalt / Glass fibre rod etc.

All proprietary reinforcing bars shall be cut, bent and installed in accordance with the Manufacturer’s published information and any appropriate product technical approval.

6.2.2 Fibre reinforcement

Unless fully described in clauses P6.2.3 & P6.2.4, details of the proposed fibres, dosage, source and suppliers shall be forwarded to the CA for agreement.

P6.2.3 Non-ferrous

reinforcement shall be used in the following locations

[Text Input Here]

P6.2.4 Non-ferrous fibres

shall be used as follows

Types of fibreLocation and dosage
[Text Input Here][Text Input Here]

6.3 Execution

6.3.1 General

All reinforcement shall be fixed in position in accordance with the reinforcement detail drawings and reinforcement schedules. Any alterations of reinforcement shall be carried out only with the prior written agreement of the CA.

6.3.2 Reinforcement handling

6.3.2.1 Storage

All reinforcement shall be delivered in properly identified QR coded or similarly tagged bundles, reinforcement mats or pre-assembled welded fabrications and shall be stored on site in a manner so as not to become contaminated by deleterious materials or otherwise damaged. Fabric shall be stored flat.

6.3.2.2 Handling

Reinforcement shall not be dropped from height, mechanically damaged or shock loaded in any way.

6.3.3 Tying

All tying of steel reinforcement shall be carried out with black annealed mild steel 16 gauge tying wire, unless agreed otherwise with the CA. All ends shall be bent away from the concrete face and all loose ends shall be removed prior to placing the concrete.

6.3.4 Welding

6.3.4.1 General

The location of all welded joints shall be agreed the CA. Tack welding on site will not be permitted, unless agreed with the CA in exceptional circumstances. Provide the CA with evidence of the competence of welders and details of the welding procedures for all loadbearing welds for agreement. When welding on site ensure the welding has adequate protection from the weather. Reinforcement to be welded to structural steel shall be suitable for welding according to BS4449.

6.3.4.2 Quality

Welding procedures for on-site welding shall be agreed with the CA. Welding shall be carried out in accordance with the requirements of BS EN ISO 17660, BS 8548 and the requirements of the product approval body where applicable.

6.3.4.3 Pre-assembled welded fabrications delivered to site

The use of pre- assembled welded fabrications must be agreed in advance with the CA.
Weld All suppliers welding reinforcement shall hold a valid UKAS product approval certificate for the welding of steel reinforcement in accordance with BS EN ISO 17660, BS 8548 and the approval bodies specific requirements.

6.3.5 Projecting reinforcement

All reinforcement ends left projecting from cast concrete shall be free of contaminants and shall be protected against damage and corrosion. Light surface rusting will be accepted, unless detrimental to the finished structure or causing rust staining to adjacent exposed concrete surfaces or formwork.

6.3.6 Site bending of steel reinforcement

6.3.6.1 Conditions

Bending of reinforcement, including straightening, at temperatures less than -5 °C is not permitted.

For proprietary purpose designed “starter bar” systems site bending is to be in accordance with the manufacturer’s recommendations.

  • Bars greater than 16 diameter may not be re-bent on site.
  • The curvature should be as constant as practicable.
  • Bending should be in one operation at a constant rate.
  • Reinforcement can be warmed but not above 100 °C.
  • The bend radius shall be not less than that given in BS 8666 unless the documented re-bend properties show this can be adjusted.

6.3.6.2 Agreement

A method statement must be prepared for agreement with the CA.

6.3.6.3 Inspection

Inspect each bar bent for any sign of fracture. Any bars showing sign of fracture must be considered as non­- conforming.

Section 7 Prestressed concrete construction

Note: This section is for in-situ concrete post-tensioned construction.

7.1 Design

Design shall be in accordance with:

P7.1.1 Post Tensioning Designer

The CA / Engineer will be the Post Tensioning Designer. / The Constructor will be the Post Tensioning Designer.

P7.1.2 Design Requirements

The requirements for the prestressed construction are

[Text Input Here]

7.2 Quality control

7.2.1 General

Post-tensioning systems shall only be installed by specialist post-tensioning contractors that have the necessary experience, knowledge, resources, materials and equipment.

7.2.1.1 Post Tensioning Contractors

Post-tensioning contractors shall have CARES certification for the installation of post-tensioning systems in concrete structures against the relevant CARES Scheme Appendix or equivalent accredited product certification. All site post-tensioning activities including duct fixing, tendon installation, stressing and grouting shall be undertaken by suitably trained and experienced staff under the direct supervision of the post-tensioning contractor.

7.2.1.2 Operatives

All post-tensioning operations shall be carried out by operatives with appropriate knowledge, training and proven experience in carrying out similar operations. Supervisors and operators shall be trained and certified to meet the requirements given in CARES Appendix PT9. Trainee post-tensioning personnel shall be adequately supervised when performing post-tensioning activities.
Personnel proposed for grouting shall be suitably experienced in such work; provide details to the CA sufficiently in advance of such work to enable experience to be reviewed.
Where required by the CA the names of all post-tensioning operatives to be employed on the site shall be submitted, with their training records before commencement of the subcontract works.

7.2.1.3 Quality plan

The post-tensioning contractor shall provide the CA with a quality plan giving details of all the proposed materials, equipment and method statements relating to site activities, including work instructions quality procedures, records inspection and test arrangements and work acceptance procedures.

7.2.1.4 Audit and review

Access to the works shall be granted to CARES for the purpose of quality auditing and maintenance of certification by arrangement with the post-tensioning contractor and/or CA.
The CA may nevertheless request an additional surveillance audit on a CARES approved post-tensioning contractor by CARES, at their own cost. If a quality audit is required by the CA during the contract then this shall be clearly stated in Clause P4.4.3.1.

7.2.1.5 Stressing calculations

The post-tensioning Designer shall calculate the theoretical tendon extension. All relevant system data shall be stated e.g. µ, k, strand E value and area, wedge draw-in on lock off and any assumed movement of dead end etc. The Post Tensioning contractor shall make available for review by the CA / Engineer the actual extensions.
However, the CA may undertake the calculations but should request the values of the necessary parameters from the post-tensioning Contractor. All relevant system data shall be stated e.g. p, k, strand E value and area, wedge draw-in on lock off and any assumed movement at dead end, etc. Extension calculations shall be submitted to the CA for acceptance at least ten working days before stressing. The CA shall confirm agreement, or comment otherwise at least five working days before stressing.

7.2.1.6 Grout testing

Grout shall be CARES approved to CARES Appendix PT10 or equivalent accredited product certification and comply with the performance requirements of BS EN 447:2007 Clause 6 as follows:

Grout properties:
Fluidity BS EN 447:2007 clause 6.3 using the cone method
BleedingBS EN 447:2007 Clause 6.4 wick induced test
Volume changeBS EN 447:2007 Clause 6.5 wick induced test ≥ _0.5% and ≤ 2.5%
StrengthBS EN 447:2007 Clause 6.6 but 100mm cubes may be used
Sieve testBS EN 447:2007 Clause 6.2.
w/c ratio≤ 0.35
Grout temperatureAs specified by the grout manufacturer
Density From cube tests

Grout suitability testing shall be undertaken at the commencement of the Post Tensioning installation project and will include Fluidity, Bleed, Volume change, strength, sieve test and density testing in accordance with the above.

During the grouting works the frequency of grout testing shall be as follows:

TestFrequency
FluidityOne set of tests per grout mix at t0 and t30
Sieve testOne test per grout mix
BleedingOne wick induced test per grout mix**
Volume changeOne wick induced test per grout mix**
Strength3 100mm cubes per grouting session taken at mixer**
DensityRecorded from cube tests above**

** When using a CARES approved grout and providing the grout suitability test was satisfactorily carried out at the commencement of the project, then a repeat of the bleed and volume test is not required for every grout mix. Note however, that bleed and volume testing shall be repeated at least once every 3-month period, or sooner if there is a change in grout supplier or a significant change in conditions, e.g., water supply.

7.3 Materials

7.3.1 General

To be in accordance with the relevant parts of this Specification. Where practicable provide an EPD or equivalent confirmation of the global warming potential of each element, grout/anchorage/duct, in kgC02e/kg.

7.3.1.1 Grout

Suitability tests shall be carried out with materials, plant and personnel proposed for use on site, to verify the properties in accordance with 7.2.1.6. The tests shall be sufficiently in advance of grouting operations to enable adjustments to be made to the materials, plant or personnel.
The source of materials and procedures approved as a result of satisfactory trials shall not be departed from without the approval of the CA.
Grout shall consist of pre-bagged material requiring only the addition of a measured amount of water and shall be CARES approved to Appendix PT10.
Grout shall be stored and batched in accordance with the manufacturer’s instructions.

7.3.1.2 Strand

Strand shall comply with BS 5896. The grade and diameter shall be specified by the post-tensioning Designer and shall be obtained from firm(s) holding a valid CARES Supply and Installation of Post Tensioning Systems for Concrete Structures Scheme certificate of approval for the production of prestressing steel wires and strands to CARES Appendix PT8, or fully equivalent scheme and shall be of a type that is compatible with the anchorage testing or approval.

7.3.1.3 Stressing bar

Bar shall comply with BS 4486. The grade and diameter shall be specified and shall be obtained from firm(s) holding a valid CARES Supply and Installation of Post Tensioning Systems for Concrete Structures Scheme certificate of approval for the production of prestressing steel bars to CARES Appendix PT7, or fully equivalent scheme and shall be of a type that is compatible with the anchorage testing or approval.

7.3.1.4 Coating materials: unbonded tendons

The coating to unbonded strand shall be either high density polyethylene (HDPE) or high density polypropylene (HDPP). The coating thickness shall be at least 1.0mm unless otherwise stated in Clause P7.3.1.4.1 and the friction between the coating and the strand shall not exceed 60N/metre. The friction shall be determined in accordance with the test methods defined in EAD 160027 clause 2.2.33 “Monostrand, manufactured monostrand, friction between sheathing and strand”.

P7.3.1.4.1 Unbonded tendons

The coating material for unbonded tendons shall be

7.3.1.5 Anchorages

Anchorages for post-tensioning systems shall meet the minimum performance requirements of BS EN 13391 as defined in CARES Appendix PT3 or the post tensioning kit shall hold:

  • Either a European Technical Assessment (ETA) against EAD 160004 and be CE marked.
  • Or a UK Technical Assessment (UKTA) against EAD 160004 and be UKCA /UKNI marked.

7.3.1.6 Ducts and vents: bonded tendon

Duct, vent and connection material shall be robust enough to resist damage during construction; smooth galvanised steel with a minimum wall thickness of 0.35mm, corrugated galvanised steel with a minimum wall thickness of 0.30mm, plastic ducting conforming to the requirements of fib bulletin 75 with a minimum wall thickness of 2mm, or equivalent.

Ducting shall prevent the entrance of paste from the concrete and not cause harmful electrolytic action or any deterioration of the tendon or tendon components. The internal cross-sectional area of the duct shall be at least twice the net area of the tendon’s prestressing steel.

Ducting shall be capable of transmitting forces from grout to the surrounding concrete.

A water-resistant, fabric-based adhesive tape should effectively seal any ducts. It should be suitable for application to wet galvanised steel/ plastic ducts and to be inert and non-reactive to anything in the concrete, grout or the steel, duct or strand.

P7.3.1.6.1 Ducts & Vents

The required duct and coating for bonded tendons shall be

The following vents are to be identified and marked:

7.3.1.7 Storage and handling of materials

All materials and components are to be stored in a safe and careful manner to ensure no damage occurs to the wires or anchors. Strand is to be stored in large diameter coils prior to installation and kept away from welding and other dangerous operations and protected from extreme changes in temperature.

Strand is to be delivered to site clean and free from permanent bends, kinks, pitting, scale or other damage and to be stored in such a way as to protect it in this condition until it is installed.

If the strand is shown to have excessive corrosion it should not be used. For clarification, unacceptable corrosion is regarded as that which cannot easily be removed by hand and permanently marks the surface of the part, such as surface pitting.

7.4 Execution

7.4.1 Tendons

7.4.1.1 Location

Unbonded tendons may be deviated to avoid obstructions such as openings and columns with the agreement of the CA. The change of direction of the tendon should occur away from the opening and trimmer bars should be provided to avoid any possible cracking at the corners in accordance with TR43 Clause 6.7.

7.4.1.2 Fixing and support

Tendons shall be fixed and supported at centres not exceeding 1m and shall be securely fixed to prevent movement and flotation during the construction process.

7.4.1.3 Cutting

Tendons shall be cut to length using mechanical means.

7.4.1.4 Marking

The system of tendon location marking shall be agreed with the CA.

P7.4.1.5 Tendon location marking

The actual position of the tendon location in both plan and elevation within the slab shall / shall not be marked on the slab soffit.

7.4.2 Vents

Vents shall be fixed at injection and exit points and, where tendon drape exceeds 500mm, intermediate vents shall be fixed at tendon high points. Vents shall extend approximately 500mm above the slab surface.
All inlets and outlets shall be suitably marked to identify the tendon and their location along the tendon.
Vent spacing should not exceed 30m.

7.4.3 Cutting or drilling into prestressed slabs

Where the tendon position is not accurately and authoritatively documented, reinforcement detection equipment must be used to locate tendon positions prior to any cutting or drilling work on the slab.

7.4.4 Grout trials

Where required, full-scale grouting trials shall be carried out using the same personnel, equipment, grouting method, materials and procedures as proposed for the Works. The trial shall demonstrate that the proposed grouting method, materials and equipment fills the ducts to the satisfaction of the CA.
Trials shall be undertaken as early as possible to allow proper inspection and any necessary modifications or adjustments. The details of the trials to be carried out shall be agreed with the CA.
The trials shall reflect the actual duct geometry and shall include typical tendon arrangements. The tendons shall be nominally stressed to ensure that they assume the proper position with respect to the ducts. Trial beams shall normally be cut at five sections for examination but more sections may be specified for complex tendon profiles.
There shall be a procedure, described in the method statement, such as backup equipment or flushing out of ducts for corrective action in the event of breakdown or blockage.
Where it is agreed that a grout trial is not necessary, prior to starting work on site, inform CARES, or equivalent, of the commencement of operations and request an audit of the post-tensioning works. Provide the CA with the outcome of the audit. Should the audit highlight any areas of concern, demonstrate to the satisfaction of the CA that any works carried out before the audit are not defective.

P7.4.4.1 Grout trials

Full scale grouting trials are / are not to be carried out

[Text Input Here]

P7.4.5 Stressing

The stressing sequence, increments, and transfer strength requirements for stressing N/mm2 required are:

LocationRequirement
[Text Input Here][Text Input Here]

The Post Tensioning Designer shall provide details of the required stressing sequence and load increments.

7.4.5.2 Jacking Force

The jacking force should not exceed those given in the appropriate design standard and should be provided by the Post Tensioning Designer.

7.4.5.3 Commencement

Stressing shall not commence before the concrete has achieved the transfer strength specified by the Post Tensioning Designer that is suitable for the equipment to be used. The concrete transfer strength shall be based on match cured cubes taken at the point of concrete placement; or another method agreed with the CA.

7.4.5.4 Measurement

For routine stressing, extensions shall be measured prior to commencement of stressing, and after stressing and locking off to an accuracy of 2% or 2mm whichever is greater. Measurements shall take into consideration the possible strand movement at the dead end anchor.
The actual extensions shall be within the limits specified in BS EN 13670 Clause 7.

P7.4.5.4.1 Measurement

Load/extension graphs for more than four points on trial tendons are / are not required

The tendon ‘group’ is to be a whole panel of flat slab construction except

7.4.5.5 Completition

Tendons are not to be cut and sealed, until the Post Tensioning Designer has checked and signed off the actual extensions.
In the event that any failures occur during stressing (system components or concrete) the cause shall be thoroughly investigated and a formal report presented to the CA. No further stressing on that element shall be undertaken until the proposed corrective action has been approved by the CA

7.4.6 Stressing equipment

Stressing jacks and their load measuring system should have an appropriate and current calibration certificate, which is traceable to national standards, and no more than 6 months old at the time of stressing. The calibration shall be undertaken using equipment that has a UKAS verified check to standard. The stressing equipment shall be capable of establishing a tendon load to a maximum tolerance of +/-2%.

7.4.7 Anchorage protection

Anchorage components shall be sealed against the ingress of water or aggressive agents likely to cause corrosion of the steel or anchorage.
Unless stated in clause P7.4.7.1 the method of anchorage sealing shall be agreed with the CA.
For grouted tendons, the chosen method of sealing shall be capable of resisting the specified grout pressure.
For unbonded tendons anchorage component shall be coated with grease of similar specification to that used in the tendon and that a watertight cap be applied over the coated area. The minimum concrete end cover to the cap shall be 25mm.
Data sheets and method statements for anchorage sealing shall be submitted to the CA.

P7.4.7.1 Anchorage protection

Anchorages shall be sealed by

[Text Input Here]

7.4.8 Grouting equipment

Grouting equipment shall comply with BS EN 446 clause 7.

7.4.9 Preparation of ducts

Where necessary, all grouting and venting points shall be suitably marked to enable identification of the duct to which they are connected.
Ducts should be blown through with oil free compressed air prior to grouting, not water. Blowing through of tendons should be recorded for each tendon individually. No grout shall be placed if the temperature of the structure adjacent to the tendons is expected to be below 5°C during the following 24 hours.

7.4.10 Grouting

Grout injection shall be continuous and shall be slow enough to avoid segregation of the grout and shall comply with BS EN 446 Clause 8.

There shall be a procedure, described in the method statement, such as backup equipment or flushing out of ducts for corrective action in the event of breakdown or blockage.

All vents shall be closed one after another in the direction of the flow. The injection tubes shall then be sealed off under positive pressure of not greater than 0.1MPa.

Grouting of the ducts shall normally be shown to leave no void which has a radial dimension greater than 5% of the maximum duct sectional dimension or which poses a risk to the integrity of the tendon. Particular attention shall be given to avoiding bleed collection or void formation at high points in the ducts or anchorages.

The filled ducts shall be protected to the satisfaction of the CA to ensure that there is no damage to the grout due to shock or vibration for 24 hours after injection of the grout.

The CA or the Constructor’s representative shall be invited to witness a representative sample of the grouting operation and countersign the grouting record sheet prepared by the Post-tensioning Contractor.

Grouting to take place as soon as practicable after the tendons have been stressed, extensions approved and the strands cropped but no longer than 28 days from stressing without the approval of the CA.

If a delay to grouting is anticipated due to conditions outside of the control of the CA, then suitable protection shall be agreed with the CA and documented.

7.5 Records

7.5.1 General

One copy of the following records shall be sent to the CA not more than one week after each operation.

7.5.1.1 Anchorages

Data sheets and method statements for anchorage sealing.

7.5.1.2 Tendon installation

1 Date of installation
2 Strand source
3 Coil number
4 Heat number, or Cast number
5 Anchorage batch number
6 Duct batch number
7 Supervisor and operatives
8 Location of the products within the structure
9 Drawing number and revision status

1Date of installation
2Strand source
3Coil number
4Heat number, or Cast number
5Anchorage batch number
6Duct batch number
7Supervisor and operatives
8Location of the products within the structure
9Drawing number and revision status

7.5.1.3 Stressing

1Date of stressing
2Strength and age of concrete cubes
3The minimum age of concrete at transfer
4Wedge & barrel or anchor head, batch number
5Stressing equipment
6Calibration date
7Supervisor and operators
8Serial numbers of gauges and jacks
9Tendon identification
10Theoretical extension, actual extensions and corresponding, loads (where required), initial and final jacking loads
11Drawing number and revision status

7.5.1.4 Grouting

1The materials used, including batch numbers.
2Grout properties including grout temperatures, bleed, volume change, sieve test and fluidity in accordance with clause 7.2.1.6
3Location of each tendon that has been grouted.
4Confirmation that each tendon has been grouted.
5The date, time and weather condition - Sunny, Dry, ambient temperature etc. and structure temperatures under which the grouting operations were carried out.
6Details of any interruptions and any problems encountered during the grouting process e.g. blockages, loss of grout or loss of grout pressure.
7Supervisor and operatives
8Grout manufacturer’s Technical and Safety data sheet.
9Details of post grouting inspection, to include appropriate inspection of anchorages, end caps and vent tubes, and any remedial actions undertaken.

7.5.2 Calibration

Records shall be available and retained for all measuring equipment used on site during the Post Tensioning installation. Such equipment includes:-

  • Pressure gauges used in the grouting operation
  • Pressure gauges and associated jacks in the stressing operation
  • Temperature probes – certificates of conformity / manufacturer statements of accuracy are acceptable. These are typically supplied with the instrument on purchase.

All devices should have a clear identification which can be referenced against the calibration records and dates.

Section 8 Concrete and concreting

8.1 Concrete

8.1.1 General

8.1.1.1 Standards

Unless noted concrete shall conform to BS 8500 and BS EN 206 and shall be as specified in the appropriate Project Clauses P8.2A, P8.2B, P8.2C, P8.2D & P8.2E.

8.1.1.1.1 Standards

The use of alternative binder systems in accordance with BSI Flex 350 is / is not permitted.

8.1.1.2 Materials

All materials permitted by BS EN 206 and BS 8500-2 can be used; products shall be produced by suppliers operating a certified factory production control system. 

The chloride content of the proposed concrete including chlorides contained in the admixtures shall be limited in accordance with BS EN 206 and BS 8500-2. Provide evidence of conformity.

Calcium chloride shall not be included in any concrete.

Provide evidence of conformity to the provisions to minimise the risk of damage by alkali-silica reaction given in BS 8500-2.

Recycled aggregate (RA) and crushed concrete aggregate (CCA) shall conform to BS 8500-2.

Admixture for consistence, water resistance, colour or other specific requirement or performance shall be in accordance with BS EN 934 and TR18 A guide to the selection of admixtures for concrete by the Concrete Society.

8.1.1.3 Site changes to ready-mixed concrete

Water
Site addition of water is acceptable as part of approved procedure, prepared by the Producer and agreed in advance with the CA. For any other site addition of water, the concrete shall be deemed non-conforming and rejected. 

Other changes
No other changes to the fresh concrete shall be made after batching, without prior agreement of the CA.

8.1.1.4 Records

Submit, as appropriate, details of the proposed concretes in accordance with BS EN 206 and BS 8500-1 to the CA for approval.

For each concrete mix provide an EPD or equivalent confirmation, in accordance with BS EN 15804 and BS EN 16757, of the global warming potential of the mix in kgC02e/m3.

Daily maximum and minimum atmospheric shade temperatures shall be recorded using a calibrated thermometer(s) located close to the structure.

8.1.2 Testing

8.1.2.1 Testing of fresh concrete

Where required to be in accordance with BS EN 12350.

8.1.2.2 Conformity testing

The Concrete Producer shall carry out testing of the concrete in accordance with BS EN 206 and BS 8500 and supply copies of test results to the Constructor when requested. Where the Concrete Producer identifies a non-conformity that was not obvious at the time of delivery, this shall be reported to the Principal Contractor and the CA within 24 hours of the Constructor receiving notification.

8.1.2.3 Identity testing

The criteria for acceptance of testing carried out by the Constructor will be those given in BS EN 206 and BS 8500.

8.1.2.4 Compression testing

Concrete test cubes or cylinders shall be tested in accordance with BS EN 12390 by an independent laboratory accredited by UKAS as conforming to BS EN ISO/IEC 17025 and hold a current schedule of accreditation for the required tests.

8.1.2.5 Delivery tickets

Delivery ticket information shall be in accordance with BS EN 206 and BS 8500, as relevant and shall be completed and available before discharging concrete into the structure. Where the Constructor authorises the addition of extra water this shall be recorded on the delivery ticket; see NSCS Specification Cl. 8.1.1.3. All delivery tickets shall be retained by the Constructor until the structure is handed over to the Principal Contractor or Client. Where a ticket is marked ‘non-conforming’ a copy shall be passed to both the Principal Contractor and the CA within 24 hours of placing the concrete. 

Digital tickets shall allow non-conformance to be recorded and appropriate sign off for further actions if required.

8.1.3 Plant - ready-mixed concrete

8.1.3.1 Third-party accreditation

Ready-mixed concrete shall be supplied by a Producer from a plant including stand-by plants holding current accredited third-party certification meeting requirements of BS EN 206. Provide the CA with confirmation of the Producer’s certification in accordance with BS EN 206.

8.1.3.2 Information required

Details of a ready-mixed concrete plant proposed for use shall be forwarded to the CA. Contingency plans shall be in place prior to commencement of work should supplies be interrupted during a pour due to a plant breakdown. Where feasible, details of a suitable backup plant/supplier should be submitted to the CA for agreement.

8.1.4 Site mixed concrete

For concrete from sources other than plants holding current third-party certification, submit information to the CA that the production and conformity control systems used are in accordance with BS EN 206 and BS 8500-2.

8.1.5 Supply and transport

All concrete shall be supplied and transported to the point of discharge from the mixer/agitator truck in accordance with the requirements of BS EN 206 and BS 8500-2. Consideration should be given to transport distance and potential traffic conditions affecting delivery to site. Where appropriate, site located mixing plants may be considered.

8.2 Concretes

P8.2A Designated Concrete

Requirement
1Concrete designation[Text Input Here]
2Maximum aggregate size (mm) Enter 10, 14, 20 or 40 [Text Input Here]
3Consistence class
S1, S2, S3, S4 or other value
[Text Input Here]
4Special restrictions on cement or combination types, enter reference if required[Text Input Here]
5Special requirements for aggregates enter reference if required[Text Input Here]
6Use of coarse RA permitted?[Text Input Here]
Use of coarse CCA permitted?[Text Input Here]
Maximum mass fraction of total coarse CCA[Text Input Here]
7Requirements for accelerated or retarded set[Text Input Here]
8Special colour requirements [Text Input Here]
9Type and dosage of fibres[Text Input Here]
10Chloride class [Text Input Here]
11Minimum air content[Text Input Here]
12Method of placing concrete[Text Input Here]
13Requirement for finishing concrete - formed[Text Input Here]
Requirement for finishing concrete - unformed[Text Input Here]
14Identity testing for consistence or other properties required in accordance with BS EN 206 : 2013 Annex B and BS 8500-1: 2023 Annex B[Text Input Here]
15Agreed maximum permitted embodied carbon rating as Innovate UK classification scheme[Text Input Here]

Notes

1. All sections of this Table must be completed before any concrete is delivered to site. All parties (CA, Engineer, Principal Contractor, as appropriate) who have contributed to its production should receive copies when it is sent to the Producer as a construction issue.

2. Where ‘None’ is entered in the table this is a default value to ensure that the Table is complete. All those involved in completing the Table need to check if ‘None’ is appropriate.

P8.2B Designed concrete

Requirement
1Concrete reference[Text Input Here]
2Strength class[Text Input Here]
3Maximum water / cement ratio[Text Input Here]
4Minimum cement content kg/m3[Text Input Here]
5DC – Class where appropriate[Text Input Here]
6Permitted cement/combination types / Combined performance category[Text Input Here]
7Maximum aggregate size (mm)[Text Input Here]
8Concrete Chloride[Text Input Here]
9Target density / density class[Text Input Here]
10Consistence class [Text Input Here]
11Method of placing concrete[Text Input Here]
12Requirement for finishing concrete - formed[Text Input Here]
Requirement for finishing concrete - unformed[Text Input Here]
13Special requirements for aggregates [Text Input Here]
14Use of coarse RA permitted?
Use of coarse CCA permitted?
Maximum mass fraction of total coarse aggregate
[Text Input Here]
15Type and dosage of fibres[Text Input Here]
16Minimum air content, or other requirements to resist freeze-thaw attack[Text Input Here]
17Special requirements for temperature of fresh concrete[Text Input Here]
18Special requirements for strength development including requirements for accelerated or retarded set[Text Input Here]
19Special requirements for heat development during hydration[Text Input Here]
20Special requirements for consistence retention time[Text Input Here]
21Special requirements for resistance to water penetration[Text Input Here]
22Special requirements for resistance to abrasion[Text Input Here]
23Requirements for tensile splitting strength[Text Input Here]
24Additional technical requirement[Text Input Here]
25Identity strength testing required [Text Input Here]
26Identity consistence testing required [Text Input Here]
27Identity other properties testing required [Text Input Here]
28Digital monitoring and measurement required?[Text Input Here]
29Agreed maximum permitted embodied carbon rating as Innovate UK classification scheme[Text Input Here]

Notes

1. All sections of this Table must be completed before any concrete is delivered to site. All parties (CA, Engineer, Principal Contractor, as appropriate) who have contributed to its production should receive copies when it is sent to the Producer as a construction issue.

2. Where [None] is entered in the table this is a default to ensure that the Table is complete. All those involved in completing the Table need to check if ‘None’ is appropriate.

P8.2C Prescribed concrete

Requirement
1Concrete reference[Text Input Here]
2Cement/combination type, class and content[Text Input Here]
3Target water / cement ratio[Text Input Here]
4Consistence class [Text Input Here]
5Type, category and maximum size of aggregate [Text Input Here]
6Special requirements for density[Text Input Here]
7Concrete Chloride class or maximum chloride content of aggregate[Text Input Here]
8Required admixtures – quantity and source of material[Text Input Here]
9Additional requirements for source of material[Text Input Here]
10Requirements for proportion of fine aggregate[Text Input Here]
11Special requirements for temperature of fresh concrete[Text Input Here]
12Additional technical requirements?[Text Input Here]
13Producer to minimize risk of alkali-silica reaction[Text Input Here]
14Use of coarse CCA permitted?
Maximum mass fraction of total coarse aggregate
[Text Input Here]

Notes

1. All sections of this Table must be completed before any concrete is delivered to site. All parties (CA, Engineer, Principal Contractor, as appropriate) who have contributed to its production should receive copies when it is sent to the Producer as a construction issue.

2. Where [None] is entered in the table this is a default to ensure that the Table is complete. All those involved in completing the Table need to check if ‘None’ is appropriate.

P8.2D Standardised prescribed concrete

Requirement
1Concrete reference[Text Input Here]
2Designation[Text Input Here]
3State if concrete is reinforced[Text Input Here]
4Maximum aggregate size (mm) [Text Input Here]
5Consistence class: [Text Input Here]
6Restrictions on cement types[Text Input Here]
7Restrictions on aggregate types[Text Input Here]
8Any other special requirements[Text Input Here]

Notes

1. All sections of this Table must be completed before any concrete is delivered to site. All parties (CA, Engineer, Principal Contractor, as appropriate) who have contributed to its production should receive copies when it is sent to the Producer as a construction issue.

2. Where [None] is entered in the table this is a default to ensure that the Table is complete. All those involved in completing the Table need to check if ‘None’ is appropriate.

3. Standardised prescribed concrete produced using sulfate-resisting Portland cement is not intended to produce sulfate-resisting concrete.

 

P8.2E Proprietary concrete

Requirement
1Concrete reference[Text Input Here]
2Strength class[Text Input Here]
3Exposure class[Text Input Here]
4State if concrete is reinforced[Text Input Here]
5Consistence requirements[Text Input Here]
6Requirement for finishing concrete - formed[Text Input Here]
Requirement for finishing concrete - unformed[Text Input Here]
7Any special requirements including restrictions on constituents[Text Input Here]
8Use of CCA permitted?
Maximum mass fraction of total coarse CCA
[Text Input Here]
9Producer to provide confirmation in accordance with BS8500-1:2023 Section 5.2 that concrete complies with the above performance requirements[Text Input Here]
10Identity strength testing required [Text Input Here]
11Identity consistence testing required [Text Input Here]
12Identity other properties testing required [Text Input Here]
13Agreed maximum permitted embodied carbon rating as Innovate UK classification scheme[Text Input Here]

P8.2F Constructor variations

Details of any Constructor proposed variations to information within tables P8.2A to P8.2E

[Text Input Here]

8.3 Concreting

8.3.1 Placing and compaction

8.3.1.1 Placing

To comply with BS13670 Annex F. Concrete shall be placed and fully compacted, where required, so as to avoid cold joints, honeycombing and to minimise segregation, excessive blemishes or other defect in the hardened concrete.

For concrete cast on metal decking, when noted in Clause P10.1.1.1, slabs may be cast to a specified thickness instead of a specified level.

P8.3.1.1.1 Specialist placing systems

Placing concrete by slip forming is proposed for the following elements

[Text Input Here]

Placing concrete by jump forming is proposed for the following elements

[Text Input Here]

8.3.1.2 Compaction

To comply with BS13670 Annex F. Compaction, where required, shall be carried out without causing damage or displacement of the formwork, reinforcement, tendons, ducts, anchorages, inserts etc.

Self-compacting concrete may be considered in members with high reinforcement content or areas where proper compaction is difficult to achieve.

8.3.1.3 Kickers

When used kickers shall be made with concrete of the same strength as that used in the wall or column, of sound construction and a minimum of 100mm high; for water-resisting construction kickers should be cast monolithically with the base structure and be a minimum of 150mm.

8.3.1.4 Premature cessation

Suitable arrangements for premature cessation of a pour shall be agreed and in place before work starts. Should premature cessation of a pour arise, agree with the CA the extent and timing of any necessary remedial work before resumption of placing.

8.3.2 Concreting in extreme conditions

8.3.2.1 Cold weather

For concreting in cold weather if the predicted concrete surface temperature is likely to fall below freezing before the concrete has a strength of 5MPa then special measures should be taken during placing and curing.

Agree in advance with the CA any changes to the cement, admixtures or concrete temperature to limit extended stiffening times and maintain the required concrete strength development.

8.3.2.2 Hot weather

For concreting in hot weather, air temperature above 30°C, then special measures should be taken during placing and curing. Steel forms and reinforcement should be shaded or water sprayed to cool down the high surface temperature to avoid flash setting of concrete and early age thermal cracking.

Agree in advance with the CA any changes to the cement, admixtures or concrete temperature to minimize high temperature rises and reduction in the useful working life of the fresh concrete

8.3.2.3 High winds

For concreting in high winds special measures should be taken for protecting and curing concrete when the expected evaporation rate of water from the concrete surface is likely to exceed 1kg/m2/hr.

8.4 Curing

8.4.1 General

The Curing Class is 2 in accordance with BS EN 13670, unless otherwise specified in Clause P8.3.1.1. The surface of the concrete shall be cured to avoid premature drying out. Methods of curing shall be agreed with the CA. Curing membranes shall be compatible with any finishes to be applied subsequently.

P8.4.1.1 Curing class

Use of curing classes other than 2

ClassLocation
[Text Input Here][Text Input Here]

8.4.2 Early age thermal cracking

When concrete is to be placed in conditions or in an element where early age thermal cracking is likely, measures shall be adopted that minimise the risk of early age thermal cracking to a level acceptable to the CA. Ensure that the temperature of the concrete does not exceed 70°C and that the limiting temperature drop and limiting temperature differential do not exceed the appropriate values given in CIRIA Report C766 Sections 4.2 & 4.4 and table 7.1. Where a risk of thermal cracking is identified, the location of monitoring apparatus and interpretation of the values recorded shall be agreed with the CA prior to installation.

8.5 Inspection - post-concreting

8.5.1 General

At the end of the specified period of curing, the relevant work shall be inspected by the Constructor.

8.5.2 Water-resisting construction

For water-resisting construction, inspection shall be carried out jointly with the Constructor and CA before backfilling or covering up to determine if there are any defects which may lead to water penetration. Further inspection shall be jointly carried out to identify any water penetration after backfilling.

8.6 Surface cracking

Take all reasonable actions to minimise surface cracking, from all causes. Where cracking occurs that it is expected will result in corrosion of the reinforcement, unacceptable water leakage, impaired durability or reduced structural adequacy, it will be rectified as agreed with the CA.

Limits on cracking, unless specified in the Project Specification, are:

  • In general reinforced concrete superstructure isolated crack widths up to 0.3mm
  • In ground bearing slabs isolated crack widths up to 0.5mm between panel joints

In concrete slabs cast on metal deck formwork as part of a composite structure isolated crack widths up to 1.0 mm.

8.7 Surface finishes

8.7.1 Formed finishes

Concrete that is buried in the earth shall have a Basic finish, all other concrete shall have an Ordinary finish unless otherwise specified in the Project Specification.

8.7.1.1 Basic Finish

The requirements for a basic finish are:

Requirement
ColourNo specification requirements.
BlemishesNo specification requirements.
Extent of blowholes No specification requirements.
FormworkAny permitted
Layout & JointsAchieve specified tolerances
Flatness / Surface regularityAchieve specified tolerances as 10.9.1
TextureAny permitted
ReflectanceAny permitted
Post-finishingPermitted
ExamplesNot required
Benchmark / Mock UpNot required

8.7.1.2 Ordinary Finish

The requirements for an ordinary finish are:

Requirement
ColourNo specification requirements.
BlemishesFree from honeycombing
Extent of blowholesNo specification requirements.
FormworkAny permitted
Layout & JointsSteps at joints between forms to be a maximum of 5mm.
Flatness / Surface regularityAchieve specified tolerances as 10.9.1
TextureLargely uniform surface
ReflectanceAny permitted
Post-finishingPermitted
ExamplesSee the CONSTRUCT Ordinary Formed Example Panel for this project noted in clause P8.6.1.2
Benchmark / Mock UpNot required

P8.7.1.2 Ordinary formed finishes

CONSTRUCT Ordinary Formed Example Panel for this project at:

[Text Input Here]

8.7.1.3 Plain formed finishes

The requirements for a plain finish are:

Requirement
ColourA consistent appearance from the materials used with supply from a single source. some control of shade based on the CEM1 replacements; no discolouration from the release agent.
BlemishesNo major avoidable blemishes in the final finish including honeycombing, grout runs from adjacent pours, excessive water loss, poker burn, or aggregate bridging. as example plain project.
Extent of blowholesBlowholes are to be expected in the final finish limited to 10mm diameter distributed as example plain project.
FormworkAdjacent panels in any one visible elevation should have had the same number of uses and have the same surface type. Damaged panels that have been properly repaired may be used. Tie bolt holes to be filled flush, unless otherwise agreed.
Layout & JointsSteps at joints between forms to be a maximum of 3mm. The arrangement of fixings, formwork panels and tie-bolt holes are determined by the Constructor but should be in a regular pattern.
System formwork panel joints may be visible.
Flatness / Surface regularityAchieve specified tolerances as 10.9.1; with clean, sharp arises.
Texture Smooth and largely uniform surface from the materials used
ReflectanceMatt or sheen surface may be specified in clause P8.6.1.3
Post-finishingAvoidable surface defects and stains to be made good subject to agreeing a method with the CA.
ExamplesSee the plain formed finish example projects noted in clause P8.6.1.3
Benchmark / Mock UpA Mock Up is NOT required. A Project Physical Benchmark standard may be set based on those elements cast first.

P8.7.1.3 Plain formed finishes

The example project demonstrating the standard required for this project is [insert reference to a CONSTRUCT panel, project from MPA The Concrete Centre database or other example].

[Text Input Here]

A plain concrete finish is required where shown on Drawings Reference: [insert reference].

[Text Input Here]

Corners to be [Insert 20mm chamfer / square / other ]

[Text Input Here]

at: [insert location].

[Text Input Here]

The surface of the finish is to matt; except that a sheen is required where shown on Drawings Reference: [insert reference].

[Text Input Here]

The part of the project to be used as a Project Physical Benchmark is: [insert location].

[Text Input Here]

8.7.1.4 Special formed finishes

The requirements for a special finish will be those for a plain finish unless modified by table P8.6.1.4

P8.7.1.4 Special formed finishes

For precast concrete work a sample is/is not required.

The required special finishes are:

Requirement[Text Input Here]
Example[Text Input Here]
Colour[Text Input Here]
Blemishes[Text Input Here]
Extent of blowholes[Text Input Here]
Formwork[Text Input Here]
Joints[Text Input Here]
Tie bolts[Text Input Here]
Flatness / Surface regularity[Text Input Here]
Texture[Text Input Here]
Reflectance[Text Input Here]
Post-finishing[Text Input Here]
Benchmark[Text Input Here]
Mock Up[Text Input Here]
Drawing Reference – location of special finishes[Text Input Here]
Drawing Reference – details for special finishes[Text Input Here]

The Mock Up must be complete and available for inspection, to allow sufficient time to allow all parties to agree the project standard, allowing the possibility of requiring a second “mock up”, while achieving the lead in time required; before the start of manufacturing process for precast units or construction for in-situ concrete.

Construction of the Mock Up should use the proposed concrete, reinforcement, formwork, methods for concrete placing, compacting, etc. and personnel, to allow an assessment of the formwork quality, placing methods and other procedures.

8.7.2 Unformed finishes

A Basic finish is to be provided unless otherwise specified in the Project Specification.

Finish requirements for different surface finishes are given in the following table:

Finish
-------
Requirement
BasicOrdinaryPlainSpecial
Colour/
Blemishes
No specified requirementsNo specified requirementsMinor variations allowed. Limits on weather damage may be specified.Colour may be specified. Limits on weather damage may be specified.
Flatness / Surface regularityAs 10.9As 10.9, SR3 to BS 8204As 10.9, SR2 to BS 8204SR1 to BS 8204, or special requirement may be specified
Surface finishSlightly coarse even texture.Level, uniform, smooth or slightly textured surface.Level, smooth, uniform surface.Level, uniform surface. Any specific requirements such as tamped, polished or brushed finish may be specified.
Post-finishingPermittedPermittedPermitted subject to agreeing a method with the CA. Permitted subject to agreeing a method with the CA. Any specific requirements such as light abrasion before coating or painting may be specified.
ExampleNot requiredNot requiredNot requiredAn example may be given in the tender – Appendix A: Visual Concrete Report.
Mock UpNot requiredNot requiredNone – but a Project Physical Benchmark may be set based on those elements cast firstWill be required see Table P8.7.2.3, or a physical benchmark may be set based on elements cast first.

P8.7.2.1 Ordinary unformed finishes

An ordinary concrete finish is required where shown on Drawings Reference:
[insert reference].

[Text Input Here]

P8.7.2.2 Plain unformed finishes

A plain concrete finish is required where shown on Drawings Reference: [insert reference].

[Text Input Here]

P8.7.2.3 Special unformed finishes

Special finishes, are required as follows:

Requirement[text-input]
Standard[Text Input Here]
Colour and appearance[Text Input Here]
Blemishes[Text Input Here]
Joints- types, layout and spacing[Text Input Here]
Abrasion resistance[Text Input Here]
Chemical resistance[Text Input Here]
Slip resistance[Text Input Here]
Fibre visibility at the surface[Text Input Here]
Flatness / Surface Regularity[Text Input Here]
Post-finishing[Text Input Here]
Example[Text Input Here]
Mock Up[Text Input Here]
Drawing Reference – location of special finishes[Text Input Here]
Drawing Reference – details for special finishes[Text Input Here]

8.8 Sawn Joints in ground bearing slabs

Joints should be sawn as soon as the concrete is strong enough to be cut without damaging the arises. Unless noted on the drawings the joint depth is to be 30% of the slab thickness.

Section 9 Precast concrete

9.1 General

This section deals with additional considerations particular to structures partly or wholly of precast construction.

9.1.1 Details

The Manufacturer shall operate an agreed quality management system to BS EN ISO 9001 with Factory Production Control in accordance with the relevant product standard unless agreed with the CA. Records of the unit mark, unit composition, date of casting, and curing regime for each precast element shall be made by the Manufacturer and kept available for inspection at the precast works.

9.1.2 Connections

Connection details are to be compatible with the design assumptions and should allow for the expected tolerances, in Section 10. Details are to be submitted to the CA for agreement.

9.1.3 Erection specification and work programme

An erection specification and work programme shall be prepared and agreed with the CA.

9.1.4 Identification

For surfaces not covered by finishes all marks shall be made so that they are hidden when unit is placed in position, or may be removed without marking the concrete surface.

9.1.5 Finishes

As clause 8.6.1.2 an Ordinary finish is to be provided unless otherwise specified in the Project Specification; as clause 8.6.2 a Basic finish is to be provided unless otherwise specified in the Project Specification.

P9.1.5.1 Special formed finishes

Finishes, other than Ordinary finishes, are required as follows:

Type[Text Input Here]
Location on site[Text Input Here]
Similar finish can be seen at[Text Input Here]
Sample / special requirements[Text Input Here]

P9.1.5.2 Special unformed finishes

Finishes, other than a Basic finishes, are required as follows:

Type[Text Input Here]
Location on site[Text Input Here]
Similar finish can be seen at[Text Input Here]
Sample / special requirements[Text Input Here]

9.2 Precast concrete elements not covered by BS EN 13369

Precast concrete elements must conform to the requirements of Sections 5, 6, 7 & 8 of The NSCS Specification

9.2.1 Striking site manufactured elements

The minimum period before removing the formwork and falsework is at the discretion of the Constructor on the basis of the assessed compressive strength of the precast element.

9.3 Precast concrete products covered by BS EN 13369

Delivery notes are required for all products delivered to the site.; delivery notes must show details of product conformity, as required by BS EN 13369 and the relevant product standard.

Provide an EPD or equivalent confirmation of the global warming potential of each concrete product in kgCO2e/kg.

9.4 Lifting

No precast element shall be lifted from the base on which it was cast before the concrete has attained its design demoulding strength and is strong enough to prevent the precast element from being damaged, overstressed or distorted giving regard to the demoulding equipment to be used.

9.5 Handling and storage

9.5.1 General

Precast elements shall be clearly marked before handling in accordance with the erection specification to indicate their weight, location and orientation in the works in order to facilitate correct erection. Where delivery cannot be timed for direct final positioning, arrange suitable storage to ensure no deterioration or damage. Storage shall be on firm and uniform supports ensuring units are clear of the ground. Provide the CA with the storage proposals.

9.5.2 Protection

Precast elements faces to be exposed in the finished construction are to be protected from mechanical damage, dirt, staining, rust marks and other disfiguration.

9.5.3 Reinforcement and fixings

The Manufacturer shall determine the need for any additional reinforcement or fittings necessary for handling their precast elements or other provisions required for temporary structural purposes until the precast elements are incorporated into the structure, including details for the making good of any provision made for lifting etc.
Any inserts or fixings required to be cast within the concrete and permanently exposed either externally or within the damp cavity of the building envelope shall be of a suitably durable material unless otherwise accepted by the CA. Any other protective treatment shall be as agreed with the CA.

9.6 Placing and adjustment

9.6.1 Temporary stability

Ensure that any precast concrete element to be incorporated into the structure shall be kept stable in its erected position until such time as the element can safely carry the construction loads without distress. The overall stability of the structure shall be maintained at all times during the erection process.

9.6.2 Bearings for proprietary precast products

Are to be level and not less than the minimum recommended by the Manufacturer.

9.6.3 Cutting and drilling precast elements

Submit proposals, agreed with the Manufacturer for products, for acceptance by the CA.

9.6.4 Alignment of units

The units shall be positioned in the frame to the tolerances given in Section 10, Geometric tolerances.

9.7 Jointing

9.7.1 General

All jointing to be as shown on the erection drawings and specification agreed with the CA.

9.7.2 Concrete/grout infill

Thoroughly clean and wet surfaces of precast elements, place concrete or grout, avoiding segregation, and compact thoroughly to eliminate voids. Ensure that precast elements do not move until concrete or grout has gained sufficient strength.

9.7.3 Hybrid concrete construction

Thoroughly clean and wet surfaces of precast elements. Place, compact and cure in-situ concrete. Ensure that precast elements do not move until concrete has gained sufficient strength.

9.7.4 Materials

Grout material to comply with BS EN 197-1 and BS EN 13139.

P9.8 Information Required

This information is to be provided for precast concrete works.

Details to be providedAt Tender
Y/N
Timely, before production Y/N
Production plantDetails[Text Input Here][Text Input Here]
QA certification[Text Input Here][Text Input Here]
LiftingMethod[Text Input Here][Text Input Here]
Equipment details[Text Input Here][Text Input Here]
Design of lifting point /devices[Text Input Here][Text Input Here]
Location of lifting devices[Text Input Here][Text Input Here]
HandlingMinimum age[Text Input Here][Text Input Here]
Additional reinforcement[Text Input Here][Text Input Here]
Storage details[Text Input Here][Text Input Here]
Transport details[Text Input Here][Text Input Here]
ErectionSpecification[Text Input Here][Text Input Here]
Work programme[Text Input Here][Text Input Here]
Temporary supports/
details
[Text Input Here][Text Input Here]
Details of protection[Text Input Here][Text Input Here]
ConnectionsDetails[Text Input Here][Text Input Here]
Loads[Text Input Here][Text Input Here]
Fire resistance[Text Input Here][Text Input Here]
Preparation[Text Input Here][Text Input Here]
Grouting/packing[Text Input Here][Text Input Here]
Removal of temporary shims etc.[Text Input Here][Text Input Here]
ConcreteDesignation[Text Input Here][Text Input Here]
EPD / responsible sourcing documentation as 9.3Enter requirements[Text Input Here][Text Input Here]

P9.9 Deflection Allowances

Design pre-camber required for precast concrete elements:

[Text Input Here]

Section 10 Geometric tolerances

10.1 General

The tolerances given in this section are NOT cumulative. Unless specifically noted as specific plus and minus deviation all values given are plus or minus.

Carry out regular checks on the structure. If an element size or position is out of tolerance propose remedial measures for agreement with the CA.

P10.1.0.1 As-built geometry

The overall concrete dimension shall be checked

List of requirementsFrequency
[Text Input Here][Text Input Here]

P10.1.0.2 The cover to reinforcement shall be checked.

List of requirementsFrequency
[Text Input Here][Text Input Here]

10.1.1 Precedence

The following are the permitted tolerances for the structure as defined on the drawings. These tolerances take precedence over those given in BS EN 13670. All appropriate BS EN 13670 tolerances have been repeated for completeness of the NSCS Specification. The tolerances for position refer to the tolerance from the reference lines and datum given in Clause P1.5. Any deviation in secondary lines are included in the tolerances given. The hierarchy of tolerance adopted in the NSCs is such that the tolerance of each level must be contained within the tolerance level of the level above where 1 is the highest level:

  • First – The overall tolerance of the structure, Cl. 10.2, 10.3 and 10.4
  • Second – The positional tolerance of all parts of elements of the structure within the overall tolerance, Cl. 10.5 and 10.6
  • Third – The dimensional tolerance of the individual elements within their positional tolerance, Cl. 10.7, 10.11 and 10.12
  • Fourth – The position tolerance of reinforcement and fixings within the individual elements dimensional tolerance, Cl. 10.8, 10.9 and 10.10

10.1.1.1 Precedence

Slabs cast on metal decking are to have: a constant thickness in accordance with 10.7.1 / a finished level in accordance with 10.9.1.

10.1.2 Tolerance class

BS EN 13670 defines normal tolerances as Class 1 and this sets minimum limits for structural safety. The NSCS tolerances given in this section are Class 2.

Any project variations to meet requirements of the construction method, design, fit requirements or any other reason shall be considered Class 3 and the required deviations are given in the Project Specification.

Class 3 tolerances specified in Clause 10.13 may apply to the whole structure or any part.

10.1.3 Execution class

Where Class 3 tolerances are given in the Project Specification the execution will be to Execution Class 3.

P10.1.3.1 Execution Class 3 Tolerances

The following Class 3 tolerances should be provided as shown:

[Text Input Here]

10.1.4 Measurement

The tolerances given in Cl. 10.2.2, 10.6.5, 10.6.6 & 10.9.1 below apply before the striking of the formwork. The tolerances given are before deformation caused by loading and time-dependent effects. Floor levels and the floor flatness shall be checked on a 3m by 3m grid.

10.1.5 Reference grids

The ‘box principle’ can be applied to the tolerances in the NSCS Specification. Where it is applied to the whole building the tolerances is as given by Cl. 10.2.1; where it is applied to an individual element the tolerance is± 20 mm.

10.1.6 Box principle

The ‘box principle’ can be applied to the tolerances in the NSCS Specification. Where it is applied to the whole building the tolerances is as given by Cl. 10.2.1; where it is applied to an individual element the tolerance is± 20 mm.

10.2 Overall structure

10.2.1 Inclination

Location of any column, wall or floor edge, at any storey level, from any vertical plane through its intended design centre at ground floor level in a multi-storey structure.

Permitted deviation Δ = the smaller of 50mm or H/(200n1/2) mm

where h = free storey height in mm

H = free height at location = Σhi in mm

n = number of storeys where n > 1

10.2.2 Level

Level of floors at supports measured relative to the intended design level at the level being checked.

Permitted deviation D for

H < 10m =15mm

10 m < H < 100 m =0.5(H + 20) mm H > 100 m =0.2(H + 200) mm

where H = sum of the intended storey heights in m

10.3 Base support: foundations

Base supports shall include direct foundations and pile caps, etc. but not deep foundations such as piles, slurry walls, diaphragms, special anchorages, etc.

10.3.1 Plan section

Permitted deviation Δ = 25 mm

where lx = intended position in the x direction

ly = intended position in the y direction

10.3.2 Vertical section

Position in the vertical direction of a base support relative to the intended design position.

Permitted deviation Δ = 20mm

where supporting concrete superstructure

Permitted deviation Δ = -15mm+ 5mm where supporting steel superstructure

where h = intended distance of foundation below datum level

10.4 Foundation bolts and similar inserts

Note: Deviations are coordinated with BS EN 1090-2: 2008 Cl. D.2.20.

10.4.1 Preset bolt prepared for adjustment

  • Distance of centre of a bolt group from intended design position Permitted deviation = 6 mm
  • Location of bolt at tip, from centre of bolt group Permitted deviation ΔY, ΔX = 10 mm
  • Protrusion

Permitted deviation ΔP. : -5mm > ΔP <25mm

10.4.2 Preset foundation bolt not prepared for adjustment

  • Distance of centre of a bolt group from intended design position Permitted deviation = 3 mm
  • Location of bolt at tip, from centre of bolt group Permitted deviation ΔY, ΔX = 3 mm
  • Vertical protrusion Permitted deviation ΔP. : -5mm > ΔP <45mm
  • Horizontal protrusion Permitted deviation ΔX. : -5mm > ΔX <45mm

10.5 Elements - columns and walls

The deviation or sum of any deviations of any individual element must not exceed the overall building structure tolerance given in 10.2

10.5.1 Position on plan

Position of the element edges and centre line relative to:

  • At base level the intended design position.
  • At any upper level the actual location of the element at the level below.

Permitted deviation Δ =10mm where L = distance to centreline from grid line

10.5.2 Verticality by storey of the structure

Inclination of a column or wall at any level in a single- or multi-storey building.

Permitted deviation Δ for

h <: 10 m = the larger of 15mm or h/400 h > 10 m = the larger of 25mm or h/600

where h = height of element in mm

10.5.3 Offset between floors

Deviation between centrelines at floor level.

Permitted deviation Δ = the larger of 10mm or t/30 mm, but not more than 20mm where t = thickness in mm = (t1 + t2)/2

10.5.4 Curvature between adjacent floors

Curvature of an element between adjacent storey levels.

Permitted deviation Δ for

h <: 70 m = the larger of 15mm or h/400 h > 10 m = the larger of 25mm or h/600

where h = height of element in mm

10.5.5 Level per storey of structure

Level of adjacent floors at supports.

Permitted deviation Δ =10mm where h = storey height in mm

10.5.6 Distance between adjacent columns and walls

Dimension of free space between adjacent columns and walls.

Permitted deviation Δ = the larger of 20mm or L/600 but not more than 40mm, where L = distance between the elements in mm.

10.6 Elements - beams and slabs

10.6.1 Location of beam to column connection

Location of a beam to column connection measured relative to the column.

Permitted deviation Δ = the larger of 20mm or b/30mm

where b = dimension of column in the same direction as Δ in mm

10.6.2 Position of bearing axis of support

Position of bearing axis of support when structural bearings are used.

Permitted deviation Δ = the larger of 15mm or L/20mm

where L= intended distance from edge in mm

10.6.3 Straightness of beams

Horizontal straightness of beams.

Permitted deviation Δ = the larger of 15mm or L/60mm

where L= distance between supports

10.6.4 Distance between adjacent beams

Distance between adjacent beams, measured at corresponding points.

Permitted deviation Δ = the larger of20mm or L/600mm, but not more than 40mm

where L = distance between support centrelines in mm

10.6.5 Inclination of beam or slab

Difference in level across a beam or slab at corresponding points in any direction.

Permitted deviation Δ = (10 + l/ 500) mm

where L= span of element in mm

10.6.6 Level of adjacent beams

Level of adjacent beams, measured at corresponding points.

Permitted deviation Δ = (10 + L/500) mm

where L = distance between support centrelines in mm

10.6.7 Position of slab edge

  • At base level position of slab edge relative to intended design position.
  • At upper levels position of slab edge relative to actual slab edge position on the floor below.

Permitted deviation Δ = 10 mm

10.7 Section of elements

10.7.1 Cross-section dimension of elements

Applicable to beams, slabs, columns and other elements covering length, breadth and depth.

Permitted deviation Δ = for

l < 150 mm = 10mm I = 400 mm = 15mm I > 2500mm = 30mm

with linear interpolation for intermediate values where 11, 12 = intended dimensions

10.7.2 Squareness of element

Applicable to beams, slabs, columns and other elements.

Permitted deviation Δ = the larger of 10mm or L/25mm, but not more than 20mm where L= length in mm

10.8 Position of reinforcement within elements

10.8.1 Location of reinforcement

The tolerance of cover to reinforcement within an element.

Permitted deviation Δ(plus) for

h < 150 mm = +10 mm

h = 400 mm = +15 mm

h>: 2500 mm = +20 mm

with linear interpolation for intermediate values

Permitted deviation Δ(minus) = 10mm

where cmin = required minimum cover

cnom = nominal cover given on drawings

Δ = permitted deviation from cnom

h = height of cross section

For foundations and members in foundations, permitted plus-deviations may be increased by 15mm Minus­ deviations are 15mm cast against blinding or prepared earth and 50mm when cast directly against earth faces.

10.8.2 Length of reinforcement lap joints

Permitted minus-deviation Δ = 0.06L mm

where L = intended lap length in mm

10.8.3 Location of reinforcement and ducts in prestressed elements

  • Anchorages
    Permitted location deviation Δ = 25mm horizontally 5mm vertically
  • Tendons
    Permitted deviation Δ Horizontally
    in beams = 0.03h {width) > 5mm< 30mm
    in slabs = 150mm
    Vertically Δ(plus) If h < 200mm = +h/40
    If h > 200mm = +15mm
    Δ(minus) all h = -10mm
    where h for vertical section = depth in mm
    h for plan section= width in mm
    y = intended location in mm

10.9 Surface straightness

10.9.1 Flatness for floors, where an FM classification is not required

Flatness of surface of any element. Finish type as table 8.6.1 or 8.6.2

  • Basic unformed surface
    Permitted global deviation = 15mm
  • Ordinary unformed surface as SR3
    Permitted global deviation Δ = 10mm
    Plain unformed surface as SR2
    Permitted global deviation Δ = 5mm
    Special unformed surface as SR1
    Permitted global deviation Δ = 3mm
  • Ordinary formed surfaces
    Permitted global deviation Δ = 9mm Permitted local deviation D = 5 mm
  • Plain formed surfaces
    Permitted global deviation D = 9mm Permitted local deviation D = 3 mm

Flatness of surface of any element; where the global deviation D is measured under a 2m long straight edge and the local deviation D is measured under a 200mm long straight edge.

10.9.2 Flatness for floors, where an FM classification is not required

  • Basic unformed surface
    Permitted global deviation = 15mm
  • Ordinary unformed surface as SR3
    Permitted global deviation Δ = 10mm
  • Plain unformed surface as SR2
    Permitted global deviation Δ = 5mm
  • Special unformed surface as SR1
    Permitted global deviation Δ = 3mm

The global deviation D is measured under a 2m long straight edge

10.9.3 Flatness for floors where Concrete Society TR34 FM classification is required

FM ClassProperty EProperty F
14.51.8
26.52.0
38.02.2
410.02.4

10.9.4 Edge straightness

Straightness of edge of floor slab or element.

Permitted deviation Δ for

L < 1 m = 8 mm L > 1 m = 8 mm/m, but no greater than 20 mm

where L = length of edge

10.10 Openings and fixings

10.10.1 Openings

Size and location of opening relative to actual location of element.

Position
Permitted deviation Δ1 = 10 mm, where L1 = intended distance to centre line
Size
Permitted deviation Δ2 =
L2 < 150mm = 6 mm
L2 = 400mm = 15 mm
L2 > 2500mm = 30 mm
with linear interpolation for intermediate values, where L2 = intended dimension

10.10.2 Cast-in bolts

Location of fixing or groups.

  • Location of fixing or groups relative to either the intended design position at the base level, or the actual position of the element they are cast into at any upper level. Permitted deviation Δ1 = 6mm where L1 = distance between bolt groups
  • Internal distance between fixings in a group relative to the intended design distance. Permitted deviation Δ2 = 3mm where L2 = distance between bolts

Protrusion of fixing

Permitted deviation = Δ(plus) + 25 mm, Δ(minus) – 5 mm

10.10.3 Cast-in channels

Location of channels

  • Location of edge of channel relative to either the intended design position at the base level, or the actual position of the element they are cast into at any upper level.
    Permitted deviation Δ1 = 10mm
  • Length of channel relative to the intended design distance
    Permitted deviation Δ2 = 10mm
  • Protrusion of fixing

Permitted deviation Δ1 = 5 mm
Inclination Δ2 = 5 mm

10.10.4 Cast-in fixings

Location of fixing or groups relative to either the intended design position at the base level, or the actual position of the element they are cast into at any upper level.

  • Deviation in plane
    Permitted deviation Δ1 = 10 mm
  • Deviation in depth
    Permitted deviation Δ2 = 10 mm

Note: Deviation in plane can be to a vertical or horizontal surface.

10.11 Staircases

The permitted deviation in the height of any riser is 5mm of the intended design value. The permitted deviation in the length of any going is 5mm of the intended design value.

10.12 Precast concrete elements

10.12.1 Standard precast products

Standard precast products shall comply with the tolerances given in the relevant product standards.

10.12.2 Project designed precast elements

Concrete elements produced for the project shall comply with the tolerances for: sections of elements; position of reinforcement within elements; surface straightness; and openings and fixings given above.

10.12.3 Joints between precast elements

Unless otherwise agreed the width of joints between units shall not be more than 10mm.

P10.12.4 Joint Widths

The tolerance on the width of joints between precast elements is shown on drawing: [insert numbers].

[Text Input Here]

P10.13

[Text Input Here]